Process for mounting gas pipelines of gas vertical shafts
A pipeline installation and gas pipe technology, which is applied in the direction of gas discharge, safety devices, wellbore/well components, etc., can solve the problems of low cost, filling problems after the lower port annulus seals the gas pipe wall, and reduces construction costs , The effect of shortening the construction period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0028] In order to illustrate the present invention more clearly, the present invention will be further described below in conjunction with preferred embodiments and accompanying drawings. Similar parts in the figures are denoted by the same reference numerals. Those skilled in the art should understand that the content specifically described below is illustrative rather than restrictive, and should not limit the protection scope of the present invention.
[0029] In this embodiment, the gas drainage well of Shihao Mine of Chongqing Songzao Coal and Electricity Company is taken as an example. The gas drainage shaft gas pipeline installation process of the gas drainage shaft includes the following steps:
[0030] (1) Gas shaft 14 is excavated. In this embodiment, the gas shaft 14 is constructed by raising the drilling rig, and the pilot hole is reamed into a gas shaft 14 with a diameter of 1.65m. 20m 3 / h, the hole bottom deviation is 0.54%. During the construction process,...