Pre-buried pipeline anchor sealing construction method of reversed anchor pocket
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- CCCC SECOND HARBOR ENG
- Publication Date
- 2017-07-11
Smart Images

Figure 1 
Figure 2
Abstract
Description
technical field
[0001] The invention relates to the field of prestressed construction. More specifically, the present invention relates to a pre-embedded pipeline anchor sealing construction method with undercut anchor holes. Background technique
[0002] Before the prestressed concrete structure is subjected to the external force load, it is artificially pressured, and the resulting prestressed state is used to reduce or offset the tensile stress caused by the external load, that is, by means of the higher compressive strength of the concrete. Strength to make up for its lack of tensile strength, to achieve the purpose of delaying the cracking of concrete in the tension area, and it is more and more widely used in various construction projects, especially in the construction process of cable bridges. However, Since the anchorage is fixed on the lower slope of the prestressed structure, the anchor hole exists on the concrete surface in the form of an undercut. If the conven...