Problems solved by technology

[0006] The technical problem to be solved by the present invention: Aiming at the problems of long hardening period and poor fluidity of the current cement-based grouting materials, a preparation method of the grouting materials is provided

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for preparing grouting material

Examples

Experimental program
Comparison scheme
Effect test

preparation example Construction

[0024] A preparation method of a grouting material, the preparation method comprising the steps of:

[0025] (1) Mix calcium carbide slag with water evenly at a mass ratio of 1:3, let it stand for 30 minutes, remove the floating matter, then adjust the pH to 5.0~5.5, perform ultrasonic oscillation, filter, collect the filter residue, and press the filter residue and fly ash The mass ratio is 1:3~5, put it into an electric melting furnace for melting, the melting condition is under the atmosphere of carbon dioxide, the melting temperature is 1900~2100°C, melting for 1~2h, and collecting the molten mixture;

[0026] (2) Put the molten mixture and additives into a ball mill at a mass ratio of 6:1~2 for ball milling at 1100r / min for 50 minutes, collect the ball mill, mix the ball mill with water at a mass ratio of 1:3, and place at -30~ Carry out at -20°C for 7~9h, pulverize, pass through a 200-mesh sieve, and collect the sieved particles;

[0027] (3) According to parts by weigh...

Embodiment 1

[0030] The additive is prepared by mixing vermiculite and boehmite at a mass ratio of 2:1.

[0031] The choice of water reducer is polycarboxylate high-performance water reducer (purchase: Shandong Huawei Yinkai Building Materials Technology Co., Ltd.).

[0032] The auxiliary agent is benzoin ether.

[0033] The anti-cracking agent is SY-G high-performance expansion anti-cracking agent (purchase: Zhongxing New Building Materials Co., Ltd.).

[0034] A preparation method of a grouting material, the preparation method comprising the steps of:

[0035] (1) Mix calcium carbide slag with water evenly at a mass ratio of 1:3, let it stand for 30 minutes, remove the floating matter, then adjust the pH to 5.5, perform ultrasonic oscillation, filter, collect the filter residue, and mix the filter residue and fly ash according to the mass ratio 1:4, put it into an electric melting furnace for melting, the melting condition is under the atmosphere of carbon dioxide, the melting temperat...

Embodiment 2

[0040] The additive is prepared by mixing vermiculite and boehmite at a mass ratio of 2:1.

[0041] The choice of water reducer is HSB aliphatic high-efficiency water reducer (purchase: Qingdao Hongxia Polymer Material Co., Ltd.).

[0042] The auxiliary agent is Michler's ketone.

[0043] The anti-cracking agent is SY-G high-performance expansion anti-cracking agent (purchase: Zhongxing New Building Materials Co., Ltd.).

[0044] A preparation method of a grouting material, the preparation method comprising the steps of:

[0045] (1) Mix calcium carbide slag with water evenly at a mass ratio of 1:3, let it stand for 30 minutes, remove the floating matter, then adjust the pH to 5.5, perform ultrasonic oscillation, filter, collect the filter residue, and mix the filter residue and fly ash according to the mass ratio 1:5, put it into an electric melting furnace for melting, the melting condition is under an atmosphere of carbon dioxide, the melting temperature is 2100 ° C, melt...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a method for preparing a grouting material, and belongs to the field of building materials. Calcium carbide slag is used as an additive to improve the performances of fly ash,the calcium carbide slag and the fly ash are melted at a high temperature to achieve full melting in order to improve the grouting rate of the grouting material and shorten the grouting time; the obtained melt is mixed with vermiculite and boehmite, the water absorption expansion performance of the vermiculite improves the grouting effect, an ion channel formed between the vermiculite and boehmitemakes calcium ions in the obtained molten mixture exchange and flow in order to promote the activity and shorten the curing time, and the properties of boehmite are used to increase the flowability and the permeability of the grouting material; and the obtained mixture is then mixed with an assistant, sepiolite and the like, the water absorption expansion performance of the sepiolite makes the sepiolite become soft, and the added assistant excites the solidifying performance of the grouting material, so the problems of long setting period and poor fluidity off existing cement-based grouting materials are solved.

Description

technical field [0001] The invention belongs to the field of building materials, and in particular relates to a preparation method of a grouting material. Background technique [0002] According to the method of ordinary cement mortar pouring, it usually takes more than 7 days of curing before it can be put into use. Metallurgy, chemical industry, electric power, building materials, railways, highways, bridges and other construction and equipment reinforcement anchorage and foundation grouting are often limited by the hardening and curing time of the secondary pouring of the concrete foundation. The early high-strength grouting materials are mainly composed of organic epoxy resins, which are expensive, easy to age, and highly toxic, and the effect is not ideal. [0003] In today's rapid development, rail transit has become the mainstream means of transportation, especially urban rail transit, and rail transit is now basically using ballastless track technology for construct...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): C04B28/02C04B111/70
CPCC04B28/02C04B2111/70C04B2201/50C04B18/026C04B14/042C04B24/383C04B24/32C04B14/202C04B24/023C04B24/008C04B14/303C04B2103/302
Inventor 郭舒洋徐克程依
Owner 郭舒洋
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products