Mine vertical shaft sinking derrick mobile installation method
An installation method and a mobile technology, which are applied in the directions of earth-moving drilling, supporting devices, drilling equipment, etc., can solve the problems of long straight construction period and difficult multi-layer construction, and achieve simple and easy construction methods and low construction costs. , the effect of shortening the construction period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0027] Such as figure 1 , 2 Among them, a mine vertical shaft sinking derrick mobile installation method, comprising the following steps:
[0028] s1. Construction of derrick foundation 13, installation of temporary sinking derrick 16, and installation of each sinking drawworks;
[0029] s2. In the vicinity of the temporary sinking derrick 16, without affecting the location of the sinking construction, the sinking derrick 3 is installed between the sinking drawworks, and the track 4 passing through the derrick foundation 13 is laid, and the bottom of the sinking derrick 3 passes through the slide shoe 5 and the track 4 connect;
[0030] Track 4 adopts No. 24 or No. 38 standard steel rails, and multi-layer square timber is used for sleepers.
[0031] In the preferred scheme, the rail surface of the track 4 is the same as the installation elevation of the derrick foundation 13;
[0032] The track 4 is a double track on one side, and the derrick foundation 13 is located betwe...