A kind of steel structure pre-assembly method

A pre-assembled and steel structure technology, applied in building structure, architecture, geometric CAD, etc., can solve the problems of not being able to reflect the influence of hole and bolt assembly, taking into account the activity margin, and not being able to truly simulate and reflect the assembly process, etc. Achieving reduced time and effort

Active Publication Date: 2021-09-21
山东方大杭萧钢构科技有限公司
View PDF17 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] However, in the virtual pre-assembly method of steel structures in the prior art, the cooperation between the bolts and the holes adopts the way that the center of the circle coincides with the center of the circle. There is an assembly allowance between the bolts, and the matching method of the center of the bolt and the hole and the center of the circle in the prior art cannot reflect the influence of the assembly allowance between the hole and the bolt on the actual assembly
For example, when M20 bolts are used for connection and fastening, a hole with a diameter of 24mm is generally designed to match it, so that the bolt has a 4mm movable margin in the hole, and this movable margin can allow a certain amount of assembly during the actual assembly process. The error plays a very important role, but the existing pre-assembly technology does not take this activity margin into account, so it cannot truly simulate and reflect the actual assembly process

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A kind of steel structure pre-assembly method
  • A kind of steel structure pre-assembly method
  • A kind of steel structure pre-assembly method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0044] The present invention will be described in further detail below in conjunction with the accompanying drawings.

[0045] A method for pre-assembling a steel structure, comprising the steps of:

[0046] S1. Measurement: Measure each sub-component that has been processed by a three-dimensional scanner, and generate a corresponding three-dimensional model in the computer, wherein the measured data includes the shape and size of the sub-component and each of the positioning hole systems 20 on the sub-component The diameter of each hole and the position size on the sub-component.

[0047] S2. Assembly:

[0048] a. Load the first subcomponent 1;

[0049] b. Standard bolts 10 are installed in the two holes with the relative distance farthest in the positioning hole system 20 of the first subcomponent 1, and the standard bolts 10 are tangentially matched with the holes; the above process truly simulates the steps in the actual assembly process, In the actual assembly, the ass...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a steel structure pre-assembly method, comprising the following steps: measuring and generating a sub-component model, which includes the external dimensions of the sub-component and the position dimensions of the positioning hole system on the sub-component; loading the first sub-component; The two holes with the farthest relative distance in the positioning hole system of the component are respectively loaded with standard bolts, and the standard bolts are tangentially matched with the holes; the second sub-component is installed so that the second sub-component needs to be connected with the first sub-component. The hole sleeves in the positioning hole system matched with the standard bolts are inserted into the standard bolts and tangentially matched with the standard bolts; if all the above-mentioned holes can realize the tangential fit with the corresponding standard bolts, it is qualified; if the above-mentioned holes cannot be all If it achieves a tangential fit with its corresponding standard bolt, it is unqualified. It fully considers the impact of the margin between the bolt and the hole on the actual assembly, and can more truly reflect the connection relationship between the bolt and the hole in the actual assembly.

Description

technical field [0001] The invention relates to the technical field of steel structures, in particular to a steel structure pre-assembly method. Background technique [0002] Steel structure buildings have the advantages of high strength, light weight, good seismic performance, low foundation cost, large building area, high building quality, suitable for industrialized and standardized production, not affected by the construction season, and low comprehensive cost. As a representative of green buildings, it has reached a high level in design, manufacturing and installation technologies, mastered the design and construction technologies of various complex buildings, and has built many large-scale and complex-structured steel buildings all over the country. Structural factory buildings, long-span steel structure civil buildings and railway bridges, etc., steel structures are generally made in the factory to complete the components (including enlarged components), transported t...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): G06F30/13E04B1/24E04B1/58
CPCE04B1/24E04B1/2403E04B2001/2406E04B2001/2415E04B2001/2418
Inventor 王国容刘剑范宗永王宇李坤尚滨曹龙柱张建文白长宇
Owner 山东方大杭萧钢构科技有限公司