The installation method of the pump tower triangular mast of the mark-iii type containment system

An installation method and pump tower technology, applied in the direction of ships, etc., can solve the problems of delaying the loading work of the superstructure, limiting the increase of the shipyard's production capacity, and hoisting risk production accidents, so as to shorten the loading time, reduce the dock period, and overcome the long construction period. Effect

Active Publication Date: 2022-02-22
JIANGNAN SHIPYARD GRP CO LTD
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, hoisting at the wharf stage is risky and difficult, and it is easy to cause production accidents
[0007] However, on ships that use liquefied petroleum gas as fuel, the fuel tanks are often located in non-open areas, and the lifting of the pump tower after the completion of the containment system will cause a huge delay in the loading of the superstructure
It will have an extremely adverse impact on the shipyard's control of the dock cycle, which will greatly limit the increase in the shipyard's production capacity and increase additional operating costs.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • The installation method of the pump tower triangular mast of the mark-iii type containment system
  • The installation method of the pump tower triangular mast of the mark-iii type containment system
  • The installation method of the pump tower triangular mast of the mark-iii type containment system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0100] The implementation of the present invention will be illustrated by specific specific examples below, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification.

[0101] see Figure 1 to Figure 15 . It should be noted that the structures, proportions, sizes, etc. shown in the drawings attached to this specification are only used to match the content disclosed in the specification, for those who are familiar with this technology to understand and read, and are not used to limit the implementation of the present invention. Limiting conditions, so there is no technical substantive meaning, any modification of structure, change of proportional relationship or adjustment of size, without affecting the effect and purpose of the present invention, should still fall within the scope of the present invention. The disclosed technical content must be within the scope covered. At the s...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The present invention provides a method for installing a pump tower delta mast of a MARK‑III type containment system, focusing on the preconditions, operation process, detailed explanation of hoisting, and subsequent finishing of the pump tower hoisting in advance, and at the same time overcoming various problems caused by the hoisting in advance , to overcome the problem of long construction period of the containment system, for ships with large steel structures on the upper part of the hatch enclosure, hoisting the pump tower in advance can greatly shorten the loading time and reduce the docking period, and can guide the construction of LNG ships or LNG fuel ships It is of great significance to the shipyard's period and cost control that the company will carry out the pump tower hoisting earlier to ensure a shorter loading period and give the liquid cargo system CHS and gas system FGSS a more abundant construction period.

Description

technical field [0001] The invention belongs to the technical field of ships, and in particular relates to a method for installing a pump tower triangular mast of a MARK-III containment system. Background technique [0002] GTT MARK-III / MARK-III FLEX containment system is a membrane containment system widely used in LNG carriers and dual-fuel ships. [0003] Pump tower hoisting is a major technical difficulty in the construction of liquefied gas carriers and liquefied gas powered ships, and is also an important production node. Pump tower hoisting marks the CHS (cargo handling system) or FGSS (fuel The start of construction of the gas supply system. Premature hoisting of the pump tower will cause a lot of inconvenience to the construction of the cabin enclosure system, so the pump tower hoisting is generally arranged after the installation of the main shielding in the cabin is completed or is about to be completed. [0004] The hoisting of pump towers of liquefied gas tran...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): B63B73/20
CPCB63B73/20
Inventor 杨新杰韩啸张琦弘常浩李明振杨长顺陈宇飞朱德云朱瑞霞
Owner JIANGNAN SHIPYARD GRP CO LTD