The invention provides an aerated block drilling and
pipe arranging construction technology, and belongs to the technical field of
building construction. The aerated block drilling and
pipe arranging construction technology comprises the following steps that S1, deep design is carried out, specifically, a detailed
brick arrangement drawing and a pipeline and wire box positioning arrangement drawing are provided; S2, centralized construction is carried out, specifically, according to the
brick arrangement drawing and the pipeline and wire box positioning arrangement drawing, hole forming
machining is carried out on building blocks; S3, paying off of building bodies is carried out, specifically, a building body construction
control line, an electric box horizontal center
position line, an electric box horizontal side line and the like are popped up; S4, water and
electricity pipelines are installed; S5,
brick arranging and positioning are carried out, specifically, the
mortar joint width between the bricks is adjusted according to the brick arranging drawing and the pipeline and wire box positioning arrangement drawing; and S6, brick casing
pipe matching is carried out, specifically, according to the building body width, the water and
electricity pipeline specification and the pipeline number, a building block middle drilling casing pipe is adopted. According to the aerated block drilling and pipe arranging construction technology, holes are directly formed in the building body bricks for pipe distribution, so that hollowing and
cracking of the wall body caused by reduction of the
cutting slotting problem are avoided, the construction quality is improved, the working efficiency is effectively improved, and the investment is reduced.