Construction method of switching station concrete floor
A construction method and concrete technology, which is applied in the field of concrete ground construction of switchyards, can solve problems such as no separation of construction areas, damage to cable trenches, ground depressions under equipment foundations, etc., and achieve the effect of improving the reliability of the ground
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Example Embodiment
[0016] The present invention will be described in more detail below in conjunction with the embodiments.
[0017] The present invention is a construction method for the concrete floor of a switchyard, including the following steps:
[0018] Step 1: Feed and mix in the order of crushed stone, cement, and sand. The continuous time from when all the materials enter the mixer to the start of the mixture is the shortest mixing time, and the actual mixing time is twice the shortest mixing time;
[0019] Step two, template installation,
[0020] For the steel formwork, first clean the steel formwork to ensure the smoothness of the top surface, and check the straightness of the formwork with small lines. The allowable deviation of local deformation is 3mm, and the maximum deflection of the middle part does not exceed 4mm. If it exceeds the above range, Adjust with hydraulic jack;
[0021] The wooden formwork is used in the local bends. The wood formwork uses 5cm thick dry red pine board, the w...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap