The Method of Quickly Dismantling the Pile Head by Mechanical Hole Grouting Pile
Patent Information
- Authority / Receiving Office
- CN Β· China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- DALIAN SANCHUAN CONSTR GROUP
- Publication Date
- 2017-02-08
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to the rapid removal construction of pile heads of mechanical hole-forming cast-in-place piles. Background technique
[0002] The concrete demolition process of mechanical hole-forming pile head is to use toothless saw cutting and manual demolition with pneumatic pick. This process has the following disadvantages:
[0003] 1. The traditional construction technology of cast-in-place piles leads to complete contact between the pile head steel bars and the concrete laitance. With the increase of the strength of the concrete laitance, it is difficult to peel off the pile head steel bars and concrete.
[0004] 2. When removing the concrete at the pile head, it is mainly carried out by cutting with a toothless saw and a portable pick. During the operation, the steel bars at the pile head are often cut off, resulting in damage to the steel bars. Although measures such as reinforcement are used, the steel bars at the pile foundation will ...