A steel truss and track technology is applied in the field of roof steel truss sliding track and disassembly and assembly, which can solve the problems of high lifting requirements, assembly construction, difficult positioning of large-span roof trusses, etc., and achieves the effect of avoiding high lifting requirements.
Active Publication Date: 2018-09-14
CONSTR & INSTALLATION ENG THE THIRD ENG GROUP OF CHINA RAILWAY
View PDF6 Cites 0 Cited by
Summary
Abstract
Description
Claims
Application Information
AI Technical Summary
This helps you quickly interpret patents by identifying the three key elements:
Problems solved by technology
Method used
Benefits of technology
Problems solved by technology
[0002] During the reconstruction of old station buildings, the existing operation line will be open to traffic normally, and the roof truss assembly construction cannot be carried out on the upper part. To solve this problem, the method of overall hoisting and installation of the roof in this area is usually adopted, which can maintain the existing operation. Lines are not disturbed, but the lifting requirements are high, and it is difficult to locate large-span roof trusses
Method used
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more
Image
Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
Click on the blue label to locate the original text in one second.
Reading with bidirectional positioning of images and text.
Smart Image
Examples
Experimental program
Comparison scheme
Effect test
Embodiment Construction
[0029] The present invention will be further described below in conjunction with the accompanying drawings, but the welding and hoisting processes involved in the present invention are all conventional processes, so they will not be repeated here, and only the key technologies involved in the present invention will be set forth.
[0030] Such as Figure 1-7 As shown, a roof steel truss sliding track of the present invention includes track truss 1, channel steel track 2, track truss diagonal brace 3, track truss vertical support 4, cross-shaped steel column 5, structural plate 6, track Truss upper chord 7, track truss lower chord 8, track truss web 9, longitudinal horizontal support beam 10, transverse horizontal support beam 11, track baffle 12, steel pipe diagonal brace 13, steel pipe horizontal support 14, column end stiffener 15, Column end pre-welded beam 16, electric hoist 17, cable 18, roof steel truss lower chord 19 and track truss unit 20, the column end pre-welded bea...
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more
PUM
Login to view more
Abstract
The invention relates to a roof steel truss slipping rail and a dismounting and installing method thereof. The rail mainly comprises a rail truss, a steel channel rail, a rail truss inclined strut, a rail truss vertical support, a cross shaped steel column, a structure plate, a rail truss top chord, a rail truss lower chord, a rail truss web member, a longitudinal horizontal support beam, a transverse horizontal support beam, a rail baffle, a steel pipe inclined strut, a steel pipe horizontal support, a column end stiffening plate, a column end prewelding beam, an electric block, an inhaul cable, a roof steel truss lower chord and a rail truss unit. The main dismounting and installing method comprises the following steps of (1) making of the rail truss, (2) installing of the rail truss, (3) vertical support installing of the rail truss, (4) installing of the rail truss inclined strut, (5) installing of the steel pipe inclined strut, (7) installing of the steel channel rail and (8) dismounting of the rail truss. The roof steel truss slipping rail and the dismounting and installing method thereof belong to the field of constructional engineering, and a large roof truss is placed on the rail to slide so as to solve the problem that the large roof truss is difficult to move.
Description
technical field [0001] The invention belongs to the technical field of construction engineering, and in particular relates to a roof steel truss sliding track and a disassembly method for roof steel truss sliding construction. Background technique [0002] During the reconstruction of old station buildings, the existing operation line will be open to traffic normally, and the roof truss assembly construction cannot be carried out on the upper part. To solve this problem, the method of overall hoisting and installation of the roof in this area is usually adopted, which can maintain the existing operation. The line is not disturbed, but the lifting requirements are high, and it is difficult to locate the long-span roof truss. Contents of the invention [0003] In view of the above-mentioned problems existing in the prior art, the object of the present invention is to provide a roof steel truss sliding track and disassembly method for roof steel truss sliding construction. T...
Claims
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more
Application Information
Patent Timeline
Application Date:The date an application was filed.
Publication Date:The date a patent or application was officially published.
First Publication Date:The earliest publication date of a patent with the same application number.
Issue Date:Publication date of the patent grant document.
PCT Entry Date:The Entry date of PCT National Phase.
Estimated Expiry Date:The statutory expiry date of a patent right according to the Patent Law, and it is the longest term of protection that the patent right can achieve without the termination of the patent right due to other reasons(Term extension factor has been taken into account ).
Invalid Date:Actual expiry date is based on effective date or publication date of legal transaction data of invalid patent.