Method for constructing block prefabricated pre-tensioning prestressed corrugated steel web combined box girder
A technology of corrugated steel web and construction method, applied in bridges, bridge construction, erection/assembly of bridges, etc., can solve the problems of easy transportation, hoisting and post-maintenance, so as to facilitate rapid erection, reduce self-weight, and avoid poor stability. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0033] The construction method of the block-prefabricated pretensioned prestressed corrugated steel web composite box girder of the present invention mainly comprises the following steps:
[0034] The first step is to prefabricate the I-beam unit separately (such as figure 1 ,2 As shown), the precast concrete top slab 1, the prestressed concrete bottom slab 2 and the corrugated steel web 3.
[0035] Specifically, prefabs such as image 3 For the prefabricated concrete roof 1 shown in the figure, the roof reinforcement mesh is bound first, the position and quantity of the transverse connecting bars 1.1 and the longitudinal connecting bars 1.2 are determined according to the design requirements, and then the pier top negative moment prestressed channel 1.3 and the upper shear connector The shear studs of 1.4 are installed in the steel mesh of the roof, and then the limit formwork is installed, and the concrete is poured; after the concrete reaches the design strength, the limit...