Municipal drainage pipeline construction technology

A technology for pipeline construction and municipal drainage, which is applied to sewer pipeline systems, waterway systems, water supply devices, etc., can solve the problems of reduced construction quality, complex construction conditions, and long construction period, so as to reduce construction difficulty, shorten construction period, and improve The effect of construction quality

Active Publication Date: 2017-07-25
杭州之江市政建设有限公司
View PDF4 Cites 24 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] In urban road widening and reconstruction projects, the geology is relatively complex. During construction, it is necessary to consider both the construction period and the closed traffic problem. If the construction is carried out according to the conventional construction method (grooving and sloping, slotting support), the safety of surrounding buildings cannot be guaranteed. At the same time, the constru

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0029] The following is a further description of the municipal drainage pipeline construction process.

[0030]A municipal drainage pipeline construction process, including measuring and setting out, driving steel sheet piles and dewatering, trench excavation, pipeline foundation, pipeline laying, inspection well masonry, closed water test, trench backfilling and pulling out steel sheet piles. The specific construction steps are as follows.

[0031] 1. Measurement and setting out include the following steps

[0032] Do a good job in the positioning of the trench center, the excavation sideline, and the determination of the center elevation, and encrypt the construction guide points and benchmark points, so that the positions and elevations of each process can be measured at any time during construction.

[0033] (1) Check the benchmarking points and establish a temporary benchmarking point every 60 meters;

[0034] (2) Measure the ground elevation of the pipeline, the center...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a municipal drainage pipeline construction technology. The municipal drainage pipeline construction technology is characterized by comprising the steps of measuring, paying off, piling steel sheet piles, dewatering, digging a furrow, laying a pipeline foundation, laying a pipeline, building an inspection well, conducting a closed water test, refilling the furrow and drawing out the steel sheet piles. The municipal drainage pipeline construction technology has the advantages of improving the construction quality, lowering the construction difficulty, shortening the construction period and improving the surrounding pipeline safety.

Description

technical field [0001] The invention relates to the field of urban construction engineering construction, more specifically, it relates to a municipal drainage pipeline construction technology. Background technique [0002] In urban road widening and reconstruction projects, the geology is relatively complex. During construction, it is necessary to consider both the construction period and the closed traffic problem. If the construction is carried out according to the conventional construction method (grooving and sloping, slotting support), the safety of surrounding buildings cannot be guaranteed. At the same time, the construction cost is increased, and the construction period cannot be guaranteed; in addition, in the conventional construction method, certain trench support measures are required for slotting construction. Once the construction environment changes, the construction conditions are complicated, the construction period is long, and the surrounding pipelines Sa...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E03F3/06
CPCE03F3/06
Inventor 陈少军马爱国
Owner 杭州之江市政建设有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products