A multi-functional liquid supply system for the test device of combustible ice preparation and mining
A multi-functional, liquid supply technology, applied in the direction of control/regulation system, pipeline system, and simultaneous control of multiple variables, etc., can solve problems such as difficulty in reflecting the accumulation environment, limitations in mining plan design, etc., and achieve flexible temperature adjustment of the solution , high security, fast response effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0023] Example 1: The preparation method of combustible ice with liquid injection first and then gas injection is an experimental scheme for direct liquid injection
[0024] In the preparation process of combustible ice, if the preparation method of injecting liquid first and then injecting gas is adopted, the experimental scheme of direct liquid injection can be adopted. The specific implementation plan is as follows: Before the liquid supply of the combustible ice preparation experiment starts, the V1 -V9 shut-off valves are all closed. After starting the liquid supply experiment, open the shut-off valve (V1 or V2) at the back end of the water tank (C1) or NaCl solution tank (C2) according to the predetermined solution, and start to infuse the liquid into the liquid injection pump (1). After being filled with solution, open the shut-off valve (V8) and the shut-off valve (V9) of the rear-end main pipe, and send an opening instruction to the pneumatic regulating valve (5) on t...
Embodiment 2
[0025] Example 2: The embodiment of steady-pressure liquid injection under the preparation method of combustible ice gas injection first and liquid injection later
[0026] During the preparation of combustible ice, if the preparation method of injecting gas first and then injecting liquid is adopted, the experimental scheme of steady-pressure liquid injection can be adopted. The specific implementation plan is as follows: Before the liquid supply of the combustible ice preparation experiment starts, V1-V9 cut-off valves are all closed. After starting the liquid supply experiment, open the cut-off valve (V1 or V2) at the rear end of the water tank (C1) or NaCl solution tank (C2) according to the predetermined solution, and start to infuse the infusion pump (1). After the liquid injection pump (1) is filled with solution, open the cut-off valve (V6), start the liquid injection pump to start supplying liquid, and the solution enters the initial stage of the pressure-stabilized i...
Embodiment 3
[0027] Example 3: The implementation scheme of steady-pressure heating and liquid injection in combustible ice-injection mining mode
[0028] In the combustible ice injection thermal mining experiment, the implementation scheme of steady-pressure heating liquid injection can be adopted, and the specific implementation scheme is as follows: the operation process of stable-pressure gas supply and flow adjustment operation process in this implementation scheme are the same as those in Example 2, please refer to Example 2. Subsequently, when the measured flow accumulation value reaches the required amount of the experiment, the closing command is sent to the pneumatic regulating valve (5). When the solution passes through the temperature sensor (8), the data acquisition instrument (10) acquires the temperature signal of the temperature sensor (8), transmits the signal to the industrial computer (11) and displays it. The PLC in the industrial computer (11) transmits the heating po...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 