A new type of pipe jacking and its construction method for construction of underground excavation space
A construction method and pipe jacking technology, which can be used in earth-moving drilling, mining equipment, underground chambers, etc., can solve the problems of complicated installation and disassembly, and achieve the effect of simple installation and accurate measurement.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0019] see Figure 1 to Figure 3 , the present invention provides a technical solution: a new type of pipe jacking for the construction of underground excavation space, including a pipe jacking 1 and a temperature measuring device, the temperature measuring device includes a strain gauge 2 and a transmission line 3; the pipe jacking 1 is Concrete pipe jacking, the concrete pipe jacking includes several sections, the strain gauge 2 is a temperature-sensitive strain gauge, the strain gauge 2 is connected with a transmission line 3, and a PVC pipe 4 is spirally arranged in the concrete jacking pipe before pouring , the outer diameter of the PVC pipe 4 is smaller than the wall thickness of the concrete jacking pipe, and the PVC pipe 4 and the two sides of the concrete jacking pipe are arranged in full length.
Embodiment 2
[0021] see Figure 1 to Figure 3 , On the basis of Embodiment 1, the present invention provides a construction method for a new type of pipe jacking used in underground excavation space construction, comprising the following steps:
[0022] a. First, position the pipe jacking 1, seal the PVC pipe 4 at one end of the pipe jacking 1 in the first section,
[0023] b. Then, pass the transmission line 3 with the strain gauge 2 along the PVC pipe 4 .
[0024] c. After the position of the first section of pipe jacking 1 is determined, the second section of pipe jacking 1 is connected to the transmission line 3 with the strain gauge 2 first. After connecting the transmission lines 3 on the first section and the second section, according to the corresponding position Push into the second section of the jacking pipe 1, and so on until all the jacking pipes 1 are installed.
[0025] During the operation of step c, it is tested whether the transmission line 3 can be used before each jac...