[0031] The present invention will be further described below in conjunction with the accompanying drawings and examples, but the present invention is not limited in any way, and any changes or improvements made based on the teaching of the present invention belong to the protection scope of the present invention.
[0032] The method for recovering the residual jack pillars in the high-stage and large-span goafs in the upper and lower parts of the present invention includes the steps of constructing artificial false roofs, forming a working platform, recovering by upward horizontal layered filling method, and recovering by approach filling method, specifically including:
[0033] A. Construct artificial false roof: Fill the tall goaf 2 above the residual roof column 1 to construct artificial false roof to ensure mining safety. In order to facilitate the filling construction, first construct the filling borehole on the top of the goaf, then erect the pipeline, fill the filling sl...