A Decomposition Method for Medium-Term Power Trading Plan of Cascade Hydropower Station Group

A cascaded hydropower station group and power station technology, applied in computing, data processing applications, instruments, etc., can solve problems such as overcapacity of electric power, centralized production, and difficulty in hydropower consumption

Active Publication Date: 2021-07-06
昆明电力交易中心有限责任公司 +1
View PDF9 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] Under the double pressure of the slowdown in power demand growth and the rapid growth of power installed capacity, since 2013, the power supply in Yunnan Province has changed from seasonal abundance and shortage to annual surplus. 16.8 billion, 15.26 billion, 31.4 billion, 28.7 billion. The direct reason for the difficulty of hydropower consumption is the overcapacity of electric power. The deep-seated reason is the large-scale advanced development and centralized production of power sources, and the mismatch between power supply development and the electricity market

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A Decomposition Method for Medium-Term Power Trading Plan of Cascade Hydropower Station Group
  • A Decomposition Method for Medium-Term Power Trading Plan of Cascade Hydropower Station Group
  • A Decomposition Method for Medium-Term Power Trading Plan of Cascade Hydropower Station Group

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0021] The present invention will be further described below in conjunction with the accompanying drawings and examples of implementation.

[0022] On the premise that the monthly transaction power of the power station has been determined, in order to consider fairness and ensure that the completion progress of the monthly cumulative power generation of each power station is consistent, the goal of decomposing and checking the power trading plan of large-scale hydropower station groups is to complete the monthly cumulative power generation of the day The maximum deviation between the degree and the completion degree of the system plan is the smallest, and the specific implementation method is as follows:

[0023] (1) Objective function

[0024]

[0025] In the formula, F m Indicates the maximum deviation between the monthly actual power generation completion degree and the system planned completion degree of all power stations on that day; t today and D represent the date...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention belongs to the field of reservoir dispatching and operation, and relates to a method for decomposing the medium-term power trading plan of cascade hydropower station groups. The goal is to minimize the maximum value of the deviation between the completion degree of the monthly accumulated actual power generation and the completion degree of the system plan on the current day, and it can be effectively determined by using a heuristic algorithm. The monthly transaction plan of cascade hydropower station group is decomposed into daily plan. The technical solution is: use the daily scale load and runoff forecast results to dynamically update the load and inbound flow forecast information from the current day to the end of the month, and use the objective function that minimizes the maximum deviation between the monthly actual power generation completion degree and the system plan completion degree. , to generate a set of power stations participating in the adjustment of the power generation plan, and to make rolling corrections to the subsequent day's power generation plan. The method of the present invention can meet the demand of cascade hydropower station groups for decomposing mid-term transaction electricity to daily, and effectively solves the practical problem that the current mid-term electricity transaction plan decomposition and cascade upstream and downstream water volume balance are not closely connected.

Description

technical field [0001] The invention belongs to the field of reservoir dispatching and operation, and particularly relates to a method for decomposing mid-term power trading plans of cascade hydropower station groups. Background technique [0002] Under the double pressure of the slowdown in power demand growth and the rapid growth of power installed capacity, since 2013 the power supply in Yunnan Province has changed from seasonal abundance and shortage to annual surplus. 16.8 billion, 15.26 billion, 31.4 billion, and 28.7 billion. The direct reason for the difficulty of hydropower consumption is excess power capacity, and the deep-seated reason is the large-scale advanced development and centralized production of power sources, and the mismatch between power supply development and the electricity market. In order to solve the deep-seated contradictions faced by Yunnan's power industry, Yunnan has taken the lead in carrying out market-oriented electricity transactions in th...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): G06Q10/06G06Q50/06
CPCG06Q10/06375G06Q50/06Y04S10/50
Inventor 张茂林程雄刘双全程春田周娜张俊涛马高权张一谢蒙飞刘祥瑞和佩珊申建建
Owner 昆明电力交易中心有限责任公司