Arc-shaped roof internode steel truss hoisting and mounting integrated device and butt joint hoisting and mounting method
A hoisting device and steel truss technology, which is applied in safety devices, transportation and packaging, and load hanging components, etc., can solve problems such as difficult installation of arc-shaped roof steel trusses, inability to move flexibly, and large labor consumption, etc., to achieve Low production cost, convenient installation, and improved efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0057] Such as Figure 1~Figure 3 As shown, an integrated device for hoisting and installing steel trusses between arc-shaped roof sections, which includes two tracks that are respectively fixed on the installed sections of the roof and are parallel to each other and can be used for gantry frames and installation work platforms. The gantry moving above the curved roof, the installation work platform moving below the curved roof and the fixing device for adjusting the level of the track.
[0058] The gantry comprises a gantry beam 2 and a gantry column 3 arranged at both ends of the gantry beam 2; Both sides are provided with support rods 5, and the bottom of the gantry column sleeve 4 and the support rod 5 are provided with track wheels 6 that cooperate with the track 1; the gantry beam 2 is provided with an electric hoist 7. Two rails are installed on both sides of the curved roof section, and a gantry is erected on the rails; the gantry is equipped with an electric hoist, w...
Embodiment 2
[0074] A butt-joint hoisting method, using the above-mentioned hoisting device, hoisting the roof steel trusses using a separate hoisting method, a certain distance is reserved between the two trusses as the butt joints of the two steel trusses, and so on, every two trusses A butt joint is set between the trusses. After each steel truss and corresponding supports are hoisted, the steel members connected between the nodal points are hoisted one by one.
[0075] Hoisting method, it comprises the steps:
[0076] (a) On the steel trusses on both sides of the arc-shaped roof section (that is, the hoisted section 28), use the fixing device to fix the track and adjust the level of the track, and erect the gantry;
[0077] (b) Complete the assembly of the installation operation platform on the ground, lift the assembled installation operation platform on the ground from one end of the internode to the air through the gantry frame, move to the roof installation operation plane position...