Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Construction method of main beam of steel-concrete composite beam cable-stayed bridge

A technology of steel-concrete combination and construction method, which is applied in the direction of bridges, bridge construction, erection/assembly of bridges, etc., and can solve problems such as unfavorable structural quality, combined beam installation quality and overall construction period, and high construction site requirements

Active Publication Date: 2019-07-05
CCCC SECOND HARBOR ENG +1
View PDF6 Cites 14 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

For the limited parts of the site, there is not enough pre-assembled space, and it is difficult to implement on-site pre-assembled; the overall hoisting can only be implemented when there is a better site under the bridge. For crossing unnavigable rivers, valleys, railways, highways and In environments such as bridges, it is difficult to implement the overall hoisting process; for special cable tower structures, it is also difficult to deploy truss cranes, and at the same time, there is no suitable equipment for hoisting and installation combined with beam brackets and bridge deck cranes; Parts, transportation and installation on the beam, the limitation of the hoisting work surface, affect the work efficiency; after the installation of the steel girder and the bridge deck in the previous section and the pouring of the wet joints are completed, the wet joints are under strong tension, and the bridge deck crane moves forward, and then For the installation of the next section, for seasons with low temperature or large temperature difference, the wet joints cannot be constructed normally, which greatly affects the installation efficiency of the main girder. Wet joints will have tensile stress, even cracks, cracks, etc., and the entire construction requires a long construction period, which has a great impact on the installation quality and overall construction period of the combined beam
In addition, there is a method of delaying the pouring of wet joints, which can stagger the construction of wet joints and the installation of the main girder simultaneously, but the deck crane of this method will generate relatively large compressive stress on the concrete bridge deck and tensile stress on the steel girder , which is detrimental to the structural quality
From the above content, it can be seen that the installation of the main girder of the traditional composite girder cable-stayed bridge has high requirements for the construction site, high requirements for lifting equipment, high construction energy consumption, limited work area for scattered construction, large influence of climate factors, unfavorable stress on the main structure, and poor construction efficiency. Disadvantages such as long cycle

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of main beam of steel-concrete composite beam cable-stayed bridge
  • Construction method of main beam of steel-concrete composite beam cable-stayed bridge
  • Construction method of main beam of steel-concrete composite beam cable-stayed bridge

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0034] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0035] like figure 1 The construction method of the main girder of the steel-concrete composite beam cable-stayed bridge shown in -11, the steps are as follows:

[0036]1) Install the wall-attached crane on the two cable towers 5, hoist the temporary consolidation 17 and the protection platform 18 on the wall-attached crane and install them on the cable tower 5, and erect the initial segmental steel beam on the temporary consolidation 17 3;

[0037] 2), hoist the first deck crane 1 to the steel girder 3 of the initial section by the wall-attached crane and fix it, and fix the steel beam 4 of the splicing section of the hoisting unit of the first deck crane 1 to the steel beam 3 of the initial section At both ends, the stay cables 6 of the steel beams 4 of the unit splicing section are installed and tensioned;

[0038] The fixing co...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method of a main beam of a steel-concrete composite beam cable-stayed bridge. The construction method comprises the steps: a wall-attached crane is mounted on acable tower, and initial section steel beams are hoisted by the wall-attached crane and fixed; the wall-attached crane hoists a first deck crane onto the initial section steel beams, unit splicing section steel beams are hoisted by the first deck crane and fixed to the two ends of the initial section steel beams, the first deck crane moves forwards onto the unit splicing section steel beams at oneends of the initial section steel beams, and the wall-attached crane hoists a second deck crane onto the unit splicing section steel beams at the other ends of the initial section steel beams; and the first deck crane and the second deck crane move forwards to splice the steel beams extending towards bridge side-span sections and the steel beams extending towards bridge mid-span sections and close the steel beams on the side-span sections and the steel beams on the mid-span sections. The construction method has the advantages of being high in operability, safe, reliable, controllable in quality, economical, efficient, capable of saving energy and protecting the environment and the like.

Description

technical field [0001] The invention relates to the technical field of bridge construction equipment, in particular to a construction method for the main girder of a steel-concrete composite girder cable-stayed bridge. Background technique [0002] At present, the steel girders of combined girder cable-stayed bridges are generally pre-assembled on site after leaving the factory, and the installation adopts the overall hoisting or loose assembly process. After the installation and tensioning of the concrete bridge deck is completed, move forward to enter the next stage of construction. For the limited parts of the site, there is not enough pre-assembled space, and it is difficult to implement on-site pre-assembled; the overall hoisting can only be implemented when there is a better site under the bridge. For crossing unnavigable rivers, valleys, railways, highways and In environments such as bridges, it is difficult to implement the overall hoisting process; for special cabl...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E01D21/00
CPCE01D21/00
Inventor 张鸿胡义新肖伯强王进军黄成伟胡永波赵磊代岳龙王伟张成林张亚平张波刘宁波李送根宋羽谢攀
Owner CCCC SECOND HARBOR ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products