A technology of grid structure and construction method, applied in the direction of building structure and construction, can solve problems such as affecting the normal progress of the project, large occupancy rate of structure space, cumbersome construction method, etc. Increase the effect of dimensional stability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0029] A construction method for a space grid structure engineering, specifically comprising the following steps:
[0030] Step 1. Check the positioning axis of the grid support, the specifications and positions of the support anchor bolts, the position, elevation and levelness of the top plate of the support surface, remove unqualified workpieces, and use the parts that do not meet the flatness and elevation. Flat plate;
[0031] Step 2: Weld the qualified materials, perform tensile test on the welded workpiece structure, remove the unqualified workpieces in the tensile test, identify and classify them according to the functions of different workpieces, and pack the classified workpieces Packing, transportation to the construction site;
[0032] Step 3: Determine the position of the space grid structure on the construction site according to the construction drawings, build a plurality of foundations in sequence along the outside of the space grid and parallel to the directio...
Embodiment 2
[0046] The difference from the embodiment is that in the thirteenth step, the form of one ball and two rods can also be adopted, specifically, the bottom string ball and two mutually perpendicular bottom string rods are installed at the same time to form a closed square grid, specifically:
[0047] Install the inverted triangular cone, hoist the small unit with one ball and three rods into the site, support the second oblique rod on the lower string ball, tighten the upper string rod above, make the upper string rod gradually approach the installed upper string ball, screw it in, and then Screw the slanting rod into the lower string ball hole, tighten it, and leave the other slanting rod idle;
[0048] Continue to install the bottom string ball and rod, one rod is screwed into the original bottom string bolt ball hole, one ball is at the front of the installation, and screwed in with the other oblique rod, the horizontal bottom string rod is installed in place, and both ends ar...
Embodiment 3
[0052] On the basis of the above embodiment, further, in the eighth step, the screwing-in depth of the upper chord does not affect the lower deflection of the entire grid structure;
[0053] Install the rods. During the installation process, the rods should not have initial bending, and no forced positioning and correction should be made. There should be no bending of the rods at the pressing rods;
[0054] Carry out the installation of the lower chord planar net frame, first assemble the lower chord grid, install the support in the first span, copy the column top axis, center line and elevation, and modify the error, and then install the first span Bottom chord rods and bolt balls form a longitudinal plane grid, and the pre-supply height of the bottom chord balls is adjusted by the support platform;
[0055] Arrange the temporary fulcrums to ensure the parallelism of the bottom string. According to the requirements of pre-arching, find the bottom of the slope on the temporary...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com