A three-phase integrated on-site assembly transformer assembly method
An assembly method and on-site assembly technology, applied in the manufacture of inductors/transformers/magnets, electrical components, circuits, etc., to achieve the effects of ensuring assembly quality, strengthening process inspection, and ensuring the quality of construction operations
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0027] like figure 1 As shown, a three-phase integrated on-site assembly transformer assembly method, the assembly method includes: site condition preparation before assembly, on-site transformer body assembly process, transformer acceptance test; the specific assembly method steps are as follows:
[0028] S1. Preparation of site conditions before assembly:
[0029] 1) Layout of the assembly plant. According to the on-site assembly requirements of conventional three-phase power transformer products, the temporary sealed plant is 13 meters wide, 30.5 meters long, 18.25 meters high, and 14.35 meters above sea level. It is composed of a staff lounge, and the inner and outer dustproof rooms and staff lounges are connected by doors; to ensure the cleanliness of the whole area, carpets are laid in each area; the height of the inner dustproof room is 6m, and the on-site assembly work is mainly in dustproof Indoor operation, the main door and the top can be opened, the dustproof room...
PUM
| Property | Measurement | Unit |
|---|---|---|
| length | aaaaa | aaaaa |
| height | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
Login to View More 