Method for solving HBW-rich grease mud cake in sandy gravel stratum shield tunneling
A technology of oil mud and sand and pebbles, which can be used in earth-moving drilling, mining equipment, tunnels, etc., and can solve problems such as enrichment
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0029] A method to solve the problem of HBW-rich grease mud cake in sand and pebble formation shield excavation. Due to the occurrence of HBW-rich grease mud cake in sand and pebble formation under special circumstances, it is difficult to carry out shield tunneling. First, the shield machine Select 2 of the 4 HBW injection ports to be connected to a tee as a pressure relief ball valve, and select one of the 4 EP2 injection ports to be connected to a tee as a pressure relief ball valve for sealing and decompression.
[0030] Add a high-pressure water gun to the inside of the soil tank in the mud cake detection hole of the soil tank and the ball valve of the breast plate of the soil tank, and use the high-pressure water gun to cut the mud cake rich in HBW oil in the soil tank.
[0031] Inject liquid A into the interior of the soil tank through the mud cake detection hole of the soil tank to rotate the cutter head, and after a certain period of time, inject liquid B through the b...
Embodiment 2
[0039] A method for solving the problem of HBW-rich grease mud cake in shield excavation of sand and pebble stratum, adding liquids A and B one by one, and the rest of the steps are the same as in Example 1.
[0040] Composed of the following components by mass percentage:
[0041] Liquid A: alkaline aqueous solution (35%), catalyst (0.5%), wherein the molar ratio of alkaline aqueous solution to catalyst is 1:0.05.
[0042] Liquid B: dispersant (3‰), water.
[0043] First inject the prepared A liquid 0.9m through the mud cake detection hole of the soil tank for the first time 3 , rotate the cutter head, and after 5 to 30 minutes, inject the prepared B liquid 0.9m for the first time through the chest plate ball valve. 3 , continue to rotate the cutter head.
[0044] After injecting the prepared B liquid for the first time, inject 0.9m through the mud cake detection hole for the second time 3 A liquid, continue to rotate the cutter head, inject B liquid 0.9m after 5 to 30 mi...
Embodiment 3
[0047] A method for solving the problem of HBW-rich grease mud cake in shield excavation of sand and pebble stratum, adding liquids A and B one by one, and the rest of the steps are the same as in Example 1.
[0048] Composed of the following components by mass percentage:
[0049] Liquid A: alkaline aqueous solution (50%), catalyst (0.8%), wherein the molar ratio of alkaline aqueous solution to catalyst is 1:0.05.
[0050] Liquid B: dispersant (5‰), water.
[0051]First inject the prepared A liquid 0.9m through the mud cake detection hole of the soil tank for the first time 3 , rotate the cutter head, and after 5 to 30 minutes, inject the prepared B liquid 0.9m for the first time through the chest plate ball valve. 3 , continue to rotate the cutter head.
[0052] After injecting the prepared B liquid for the first time, inject 0.9m through the mud cake detection hole for the second time 3 A liquid, continue to rotate the cutter head, inject B liquid 0.9m after 5 to 30 min...