Power-on control method and power-on control circuit for initiating explosive device drive circuit in train torpedo section

A technology of driving circuit and lightning pyrotechnics, which is applied in the field of power-on control of underwater self-launching devices, can solve the problems of limited scope of application and the inability to adjust the depth value of the mine-entering switch, and achieve the effect of reducing production costs

CN112629320AInactive Publication Date: 2021-04-09西安精密机械研究所
8 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Publication Date
2021-04-09
Estimated Expiration
Not applicable · inactive patent

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
Patent Text Reader

Abstract

The invention provides a power-on control method and a power-on control circuit for an initiating explosive device drive circuit in a train torpedo section, and solves the problems that the depth value of an existing train torpedo water entry switch cannot be adjusted and the application range is limited. During preparation of train torpedo exercise training or delivery inspection test, setting of depth parameters of the water entry switch is completed, and the set parameters are stored in a memory of a train torpedo electronic device; and during train torpedo navigation, a depth sensor outputs acquired navigation depth information in real time, and software of the train torpedo electronic device performs filtering processing on the received depth information, and is used for comprehensively judging width and depth values of a depth signal by combining a preset depth parameter of the water entry switch, and outputting a water entry starting instruction when the requirements are met. The water entry starting instruction is used as a power-on control signal to realize the power supply of a train torpedo battery and the power-on control of the initiating explosive device drive circuit.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention belongs to the technical field of power-on control of an underwater self-emitting device, and in particular relates to a power-on control method and a control circuit for a driving circuit of a pyrotechnic product in a mine operation section. Background technique

[0002] The mine operation is a special type of mine in the underwater self-launching device. The mine combat section is replaced with the mine operation section, which is used for training exercises or delivery for inspection and testing. The pyrotechnic drive circuit is the core circuit to realize the function of the mine operation section, and can complete the following functions:

[0003] 1) After the actual voyage is completed, the parking valve is ignited, the engine is stopped, and the navigation of the underwater self-launching device is terminated;

[0004] 2) Complete the ignition of the electric explosion valve for inflation, realize the inflation and expansion of th...

Examples

Embodiment Construction

[0052] Below in conjunction with accompanying drawing and specific embodiment content of the present invention is described in further detail:

[0053] like figure 1 As shown, a power-on control method for the pyrotechnic product driving circuit of the mine operation section includes the following steps:

[0054] 1) Parameter setting

[0055] Operate Leihang forward, bind the depth parameters of the water entry switch online through the CAN bus, store the depth parameters of the water entry switch in the parameter file Para. Electricity.

[0056] 2) Initialize the program of the operation thunder electronic device to obtain the depth value of the water entry switch

[0057] 2.1) Power on the electronic device of the operating mine, and initialize the program of the operating electronic device (that is, the initialization of the CAN bus interface communication); the contents of the program initialization include the CAN bus baud rate of 1Mbps, the length of the data segment ...