Double-end expansion hanging pile connecting fastener and prefab
A technology of prefabricated parts and pile buckles, applied in sheet pile walls, infrastructure engineering, construction, etc., can solve the problems of slow butt-joining piles, complicated manufacturing molds and processes, and high processing costs, achieving high work efficiency and reducing production. The effect of low cost and expense
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0017] Embodiment 1: with reference to attached Figure 1~5 . The double-headed expansion joint pile buckle is composed of two expansion nuts 1, the double-headed expansion joint body 4 and the expansion pin 7. Under the action, the expansion is hooked in the expansion hooking cavity 11 of the two expansion nuts 1 and is articulated with the boss 8 in the cavity. Have steel bar hole 9, the periphery of steel bar hole is steel bar upsetting card platform 2, and the space between card platform and strong drawing buckle is expansion joint chamber 11, sees attached figure 1 . Tension nut 1 adopts metal (as steel, stainless steel, alloy steel etc.) or non-metallic material (as plastics, synthetic plastics, pottery etc.) to make by existing casting or injection molding or pottery firing or machining technology. One or two or more expansion guide wire grooves are longitudinally opened on the wall of the guide channel of the expansion joint body of the double-ended expansion joint ...
Embodiment 2
[0018] Embodiment 2: with reference to attached Figure 6 . On the basis of Embodiment 1, the prefabricated parts (pipe piles----circular tubular, square pipe piles, etc.) composed of double-ended expansion articulated pile buckles, the two ends of the prefabricated part 12 are respectively equipped with expansion nuts 1 , the upsetting heads 10 at both ends of several longitudinal steel bars in the prefabricated part 12 are respectively clamped on the steel bar upsetting card table 2 in the expansion nut 1, and the double-headed expansion joint body 4 and the expansion pin 7 are used for two prefabricated steel bars. Butt between pieces 12. (When the double-headed expansion joint body 4 is docked with the pipe pile, the expansion joint body in the double-headed expansion joint body expands in the expansion nut 1; when the pipe pile is not docked with the pipe pile, its The double-ended expansion joint body 4 is separated from the tension nut 1 and kept separately).
Embodiment 3
[0019] Embodiment 3: with reference to attached Figure 7 . On the basis of Embodiments 1 and 2, the pile connection structure between the pipe pile and the pipe pile, or between the bridge pier and the bridge pier, or between the utility pole and the utility pole, which is formed by the double-headed expansion articulated pile buckle, the two to be docked The ends of the prefabricated parts are respectively equipped with a number of expansion nuts, and the expansion nuts are clamped with the upsetting heads at both ends of the longitudinal reinforcement in the steel cage in the prefabricated part. Pull the cavity of the nut to complete the butt joint between prefabricated parts.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com