Method for correcting incline of deep layer drill silt squeezing and soil discharging
A building and building settlement technology, applied in construction, infrastructure engineering, etc., can solve the problems of difficulty in forming radiation wells, large soil porosity, large compression deformation, etc., and achieve obvious economic and social benefits. Thorough, low-impact effect on the environment
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0018] The main structure of a residential building is a six-storey brick-concrete structure with a total building height of 16.8m and a building area of 3860m 2 , with a total length of 58.4m and a width of 10.4m, the foundation is C20 reinforced concrete strip foundation, the external wall foundation is buried at -1.65m, and the foundation is a 300mm thick stone chip cushion. Under the cushion is a soft plastic silty clay layer, the groundwater depth is -1.5m, and between -5 and 10.6m below the foundation is a highly compressed clay and silty clay soft plastic soil layer.
[0019] Observation: The building tilts 178mm to the north on average, with a tilt rate of 10.6‰, which is far greater than the specification and needs to be rectified. Adopt the present invention to carry out rectification construction to it, concrete operation is as follows:
[0020] (1) Preparatory work: Do a good job of fencing the site to prevent unrelated personnel from entering the site to interf...
Embodiment 2
[0029] A residential building was completed and put into use in December 1998. The main structure is a six-story brick-concrete structure. The total height of the building is 17.5m, the total length is 39.6m, and the width is 14.1m. The foundation is a 350mm thick reinforced concrete raft foundation. The burial depth is -1.7m, the foundation is a 100mm thick plain concrete cushion, the 500mm diameter and 10m long powder-sprayed pile composite foundation is under the cushion, the groundwater depth is -1.0m, and the height is between -5 and 10.6m below the foundation Compressed clay and silty clay soft plastic layer.
[0030]Observation: The building leans northwards by an average of 142-170 mm, with a slope rate of 8.11-9.71‰, which is far greater than the specification; the observation shows that the building is still settling, and the value of the slope is also slowly increasing, and it needs to be corrected. Adopt the inventive method to carry out rectification construction ...
Embodiment 3
[0040] An office building in Tianjin Tanggu Marine High-tech Development Zone, the building is 28.8m long, 11.7m wide and 4.5m high. The foundation is a C20 reinforced concrete raft foundation with a thickness of 250mm, and the lower part of the foundation is a C7.5 plain concrete cushion with a thickness of 100mm, and the natural foundation below it. During the decoration of the building, it was found that the maximum difference in ground elevation in the long direction (north-south direction) was 148mm. Through further observations, the building was inclined to the south at the same time, and the average inclination rate was 5.82‰. The southward inclination rate has exceeded the maximum allowable inclination value stipulated in the code. 4‰ and the slope rate is still increasing. In order to ensure the safety of the structure and reduce losses, it is necessary to rectify it in time.
[0041] Adopt the inventive method to carry out rectification construction to it, concrete ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com