Automatic production line for concrete tubular pile
A technology for concrete pipe piles and work sections, applied in sheet pile walls, grinders, construction, etc., can solve problems such as low work efficiency, inability to meet supply requirements, and high labor intensity of workers, saving time, eliminating potential safety hazards, reducing The effect of labor intensity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0019] Such as figure 1 As shown, it mainly includes feeding section 1, tensioning section 2, centrifugal section 3, room temperature steaming section 4, tensioning section 5, demoulding section 6, high-pressure steaming section 7 and steel cage assembly section 8.
[0020] Between the feeding section 1 and the tensioning section 2, there is a concrete pipe pile opening and closing chain conveyor A9 for moving the concrete pipe pile mould. The concrete pipe pile opening and closing chain conveyor A9 is mainly driven by a chain. The concrete pipe pile mold placed on the bracket is moved to realize the movement of the bracket on the bracket. The specific structure has been disclosed in the patent application number: (), and will not be repeated here.
[0021] Concrete pipe pile opening and closing chain conveyor A9, tensioning section 2, centrifugal section 3, normal temperature steaming section 4, tensioning section 5 and demoulding section 6 are equipped with concrete pipe pil...