Method for controlling sliding speed of transportation materials in chute
A chute and speed technology, which is applied in the direction of chute, transportation and packaging, etc., can solve the problems that the materials and equipment cannot be guaranteed, the speed of material sliding can not be controlled, and the material is damaged, etc., so as to achieve simple structure, eliminate safety hazards, and reduce labor intensity effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0025] A method for controlling the sliding speed of materials transported by a chute, comprising the steps of:
[0026] The first step, assemble the multi-channel chute device: see Figure 1 to Figure 5 , the multi-channel chute device with deceleration function (vertical and horizontal deceleration twice) includes a chute main body 1, a vertical deceleration plate 2, a horizontal deceleration plate 3, and a telescopic control mechanism; the chute main body 1 of multiple channels is composed of a bottom plate and 3 -21 side plates (that is, 2-20 channels), 3-21 side plates are located on the bottom plate and fixed with the bottom plate, and the adjacent side plates form chute channels (this embodiment adopts 5 chute channels , the specific number is determined according to the needs; the width of the chute channel is determined by the size of the material to be transported), the main body of the chute 1 is in an italic state with a high top and a low bottom, and the lower end...
Embodiment 2
[0055] When transporting materials with high friction in the chute, such as transporting lightweight bricks with packing boxes, cement, sand and other materials with packing bags, see image 3 , in example 2, take the cement, sand of five chute transport bags as an example, the method is:
[0056] The first step, assembling the multi-channel chute device: it is basically the same as Embodiment 1; the difference is that: the right end of the pull rod 5 is provided with a horizontal handle, the horizontal handle is provided with positioning pin holes, and the pulley seat 13 is provided with Locating bar 11, and locating bar 11 is positioned at the left side of pulley 10, and locating bar 11 is provided with locating pin hole, and locating pin 12 inserts in the locating pin hole on the horizontal handle and the locating pin hole on the locating bar 11 during use.
[0057] The second step is to open the chute channel: the construction personnel press the pedal 15 with their feet t...