Rapid pit-in-pit form erecting method in foundation slab of buried concrete structure
A technology for underground structures and base plates, applied to underwater structures, infrastructure engineering, buildings, etc., can solve the problems of cumbersome construction procedures and long construction periods, and achieve the goals of simplifying cumbersome construction procedures, saving costs, and shortening the precipitation cycle Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0030] The pit-in-pit rapid formwork method in the foundation floor of the underground concrete structure of the present invention comprises the following steps:
[0031] see now Figure 1 ~ Figure 3 , figure 1 It is a schematic plan view of a steel plate box according to an embodiment of the present invention, figure 2 for figure 1 A-A sectional view of, image 3 for figure 1 The B-B section view.
[0032] 1. The "steel box" is prefabricated, because the "steel box" is used as the outer template of the "pit in the pit", so the length and width of the "steel box" are equal to the design drawing size (net length) of the "pit in the pit" plus 2 times the thickness of the concrete (wall thickness), the height is equal to the depth of the "pit in the pit" plus a margin of about 200mm (because the thickness of the bottom layer of the underground structure is 100mm, an additional height margin is required to prevent the cement mortar from flowing into the cushion layer. For e...