Intelligent load controller for power distribution branches and control method for controller
A controller and power load technology, applied in sequence/logic controller program control, electrical program control and other directions, can solve the problem of inability to complete load and current matching judgment, evaluation, and inability to realize student power distribution control technology, etc. , to achieve the effect of good training economic benefits and strong practicability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0040] A distribution branch intelligent load controller, including a control center, a power supply unit, a drive unit, an execution unit, a data input controller, an alarm and a display unit (see figure 1 shown in the block diagram), where,
[0041] The control center is the Siemens PLC control center, which is used to command, coordinate, organize and control the components, and to receive and judge the distribution branch data input by the data input controller, and decide whether to connect the distribution branch power supply;
[0042] The power supply unit is used to provide power for the PLC control center, and the output end of the power supply unit is connected with the input end of the PLC control center;
[0043] The drive unit is used to amplify the control signal output by the PLC control center to drive the execution unit to execute the command output by the PLC control center. The input end of the drive unit is connected to the output end of the PLC control ce...
Embodiment 2
[0048] The method is to input the power of the electrical load and the rated current value of the distribution branch calculated according to the power, and the PLC control center judges whether the power of the electrical load matches the calculated rated current value of the distribution branch, and decides Whether to connect the distribution branch, so as to realize the simulation selection training of the wires and switchgear of the power supply and distribution system; the method includes the following steps:
[0049] S1. Enter the power of the electrical load;
[0050]S2. Determine whether the input is completed, if yes, go to step S3, if no, repeat step S1;
[0051] S3. Enter the rated current value of the distribution branch that matches the power of the electrical load;
[0052] S4. Determine whether the input is completed, if yes, go to step S5, if no, repeat step S3;
[0053] S5. Determine whether the input power of the electrical load matches the calculated ...
PUM