A fracturing working method for multi-stage hydraulic jet staged fracturing string
A technology of hydraulic jetting and staged fracturing, which is applied in drill pipe, casing, earthwork drilling, etc., can solve the problem of increasing construction operation cycle and operation cost, not mentioning the optional setting of packers, increasing operation Cost and operation cycle and other issues, to achieve the effect of simple fracturing work method, reducing back splash damage and reducing pipe string creep
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0089] The invention discloses a fracturing working method of a multistage hydraulic jet segmental fracturing string, the steps of which are as follows:
[0090] S1: The multi-stage hydrojet staged fracturing string should be drained and washed before going into the well;
[0091] S2: Assembling multi-stage hydraulic jet staged fracturing strings;
[0092] S3: Drill down, adjust the drilling tool to the construction position;
[0093] S4: Install the wellhead and surface pipeline, and test the pressure;
[0094] S5: Construct the first stage according to the pump injection procedure designed for fracturing construction. After the construction is completed, the oil pipe will be sprayed, and after the spray potential is weakened, 600L / min reverse circulation will be used to assist drainage;
[0095] S6: Adjust the position of the drilling tool so that the injector faces the spray point of the second section of the design, and then construct the second section according to the ...
Embodiment 2
[0104] On the basis of Example 1, when the spray gun is turned on for sandblasting and perforation, the oil pressure is abnormally low. First, compare it with the injection pressure of the previous layer. If the injection pressure drops significantly, it is judged that the nozzle erosion is serious. method:
[0105] (1) According to the operating instructions, turn on the next "injection unit" of the tool string or pull out the drill to check and replace the tool;
[0106] (2) If there is a damaged point in the multi-stage hydraulic jet staged fracturing string, pull out the drill for inspection.
Embodiment 3
[0108] As a preferred embodiment of the present invention, the present invention discloses a fracturing working method of a multi-stage hydraulic jet staged fracturing string. In the S2 step, a multistage hydraulic jet staged fracturing string is assembled The method is as follows: each stage of the multi-stage spraying tool includes a hydraulic jet packing tool and a hydraulic centralizer connected with the hydraulic jet packing tool, each stage of spraying tools is connected end to end, and the first stage of the spraying tool The hydrojet pack-off tool is connected with the righting check valve, which is connected to the eye pipe and the guide plug in turn, and the last stage of the multi-stage jetting tool is connected to the safety joint, and the oil pipe is connected to the safety joint until the wellhead.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com