Method for cooling KR desulfurized molten iron by use of pig iron
A technology for desulfurizing molten iron and iron blocks, which is applied in the field of steelmaking, can solve the problems of splashing affecting the consumption of iron and steel materials, difficulty in smelting operations, etc., and achieves the effects of solving adverse effects, meeting cooling requirements, and simple process
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0019] The incoming molten iron is hoisted to the desulfurization tipping trolley by a crane, and then driven to the processing position for slag removal, temperature measurement, and sampling. The measured temperature is 1380°C. According to production needs, the temperature of the molten iron needs to be lowered below 1320°C. Proceed as follows:
[0020] 1) Open the molten iron tank to the position where the iron block is added, and use a crane with an electromagnetic chuck (for example, the electromagnetic chuck type is MW5 series high-temperature type) to transfer the first hoisting iron block from the iron block storage area, and hoist it to the liquid level of the molten iron tank Pause at about 30cm above, use the radiant heat of the molten iron tank to bake the iron block for about 30 seconds, and release the electromagnetic suction, so that the iron block enters the molten iron by its own gravity. In the same way, continue to add the second and third hanging iron bloc...
Embodiment 2
[0023] Hoist the molten iron entering the factory to the desulfurization tipping trolley using a crane, then drive to the processing position for slag removal, temperature measurement, and sampling. The measured temperature is 1360°C. According to production needs, the temperature of the molten iron needs to be lowered below 1320°C. Proceed as follows:
[0024] 1) Open the molten iron tank to the position where the iron block is added, and use a crane with an electromagnetic chuck (for example, the electromagnetic chuck type is MW5 series high-temperature type) to transfer the first hoisting iron block from the iron block storage area, and hoist it to the liquid level of the molten iron tank Pause at about 20cm above, use the radiant heat of the molten iron tank to bake the iron block for about 50 seconds, and release the electromagnetic suction, so that the iron block enters the molten iron by its own gravity. In the same way, continue to add the second hanging iron block unt...
Embodiment 3
[0027] The incoming molten iron is hoisted to the desulfurization tipping trolley by a crane, and then driven to the processing position for slag removal, temperature measurement, and sampling. The measured temperature is 1380°C. According to production needs, the temperature of the molten iron needs to be lowered below 1320°C. Proceed as follows:
[0028] 1) Open the molten iron tank to the position where the iron block is added, and use a crane with an electromagnetic chuck (for example, the electromagnetic chuck type is MW5 series high-temperature type) to transfer the first hoisting iron block from the iron block storage area, and hoist it to the liquid level of the molten iron tank Pause at about 50cm above, use the radiant heat of the molten iron tank to bake the iron block for about 40 seconds, release the electromagnetic suction, and make the iron block enter the molten iron by its own gravity. In the same way, continue to add the second and third hanging iron blocks u...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More