A structure and method for overall removal of a pile head of a pile foundation
Patent Information
- Authority / Receiving Office
- CN ยท China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- CCCC TUNNEL ENG
- Publication Date
- 2016-08-24
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention belongs to bored cast-in-place piles for construction pile foundations, and in particular relates to a pile foundation pile head integral removal structure and method. Background technique
[0002] After the pile foundation of reinforced concrete is poured, the pile head needs to be broken, and the steel bars and acoustic tubes of the pile head are kept and exposed. The common pile head breaking method is the construction of manual chiseling: in this method, after the cap is excavated, the main reinforcement of the reinforcement cage and the acoustic measuring tube are manually chiseled out with a pneumatic pick, and then the pile head is separated, and then a large mechanical Lifting the pile head, the disadvantage of this method is: the acoustic tube is not easy to find, it is quite time-consuming; it is slow and inefficient when digging out the main reinforcement of the steel cage and the acoustic tube; the damage to the main reinforce...