A large water depth curtain grouting method
A curtain grouting and large water depth technology, applied in construction, infrastructure engineering and other directions, can solve the problems of water surface platform layout and fixing difficult water surface operation platforms, etc., to shorten the construction period and improve the construction efficiency.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0024] The present invention will be further described below in conjunction with accompanying drawing, protection scope of the present invention is not limited to the following:
[0025] A large water depth curtain grouting method, it comprises the following steps: it comprises the following steps:
[0026] S1. Construction preparation, including drilling rigs and construction equipment in place, construction personnel entering the site and determining the position of the underwater curtain grouting work surface;
[0027] S2, such as figure 1 As shown, the water surface platform is constructed, and the specific construction steps are as follows: first place pontoons 1 on the water surface of the dam, the pontoons 1 are arranged at intervals and arranged along the curtain grouting direction of the underwater curtain grouting work surface 2, and then two adjacent pontoons 1 Build a pontoon 3 between them, install the sleeve 4 on the pontoon 3, fix the vertical guide rod 7 on th...