Auxiliary vacuumizing and automatic mud jacking integrated machine for railways
An all-in-one, automatic technology, applied in the erection/assembly of bridges, bridges, buildings, etc., can solve the problems of not realizing automatic control, affecting construction quality, and large impact of manual intervention, and improving the degree of automatic operation and control. The effect of measuring accuracy and weighing accuracy is not reduced
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2017-02-22
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention belongs to the field of railway machinery, and in particular relates to a railway auxiliary vacuum automatic grouting integrated machine. Background technique
[0002] Railway grouting machines are mainly used for grouting prestressed pipelines in bridges. Pipeline grouting is one of the most important construction links in post-tensioned beams. At present, vacuum-assisted grouting technology is basically used. The currently commonly used grouting trolley lacks an automatic feeding weighing system or has defects such as inaccurate feeding and weighing, arbitrary slurry configuration, and long powder transmission stroke; the integration of equipment at both ends of the pipeline is not high, and manual intervention affects The degree of automation of the grouting operation is limited, resulting in complex grouting operations, unstable grouting process, easy residual air at the grouting end, resulting in unsatisfactory construction, and seri...
Examples
Embodiment 1
[0044] Such as Figure 6 As shown, the grouting end of the pipeline of the prestressed concrete beam is also provided with an air release pipe 33 . The slurry outlet end of the pipeline of the prestressed concrete beam is provided with a slurry outlet pipe 34 . The vacuum pipe 28, the air release pipe 33, and the grout outlet 29 are all sealed and connected to the pipes of the prestressed concrete beam, and the pipes are respectively provided with corresponding valves. The vacuuming and grouting process of embodiment one are as follows: check the valve situation of the pipeline of the prestressed concrete beam, ensure that the grouting outlet 29, the vacuum pipe 28, the air release pipe 33, and the grouting pipe 34 are all tightly connected with the pipeline, Form a sealed state, and the initial state of each valve is closed; open the valve of the vacuum tube 28 and start the vacuum pump 27 through the PLC assembly electric control box 30, and vacuumize the pipeline. When the...
Embodiment 2
[0046] Such as Figure 7 As shown, the slurry outlet end of the pipeline of the prestressed concrete beam is provided with a slurry outlet pipe 34 . The vacuum pipe 28 and the grout outlet 29 are both sealed and connected to the pipes of the prestressed concrete beams, and the pipes are respectively provided with corresponding valves. The vacuuming and grouting process of embodiment two are as follows: check the valve situation of the pipeline of the prestressed concrete beam, ensure that the grouting outlet 29, the vacuum pipe 28, the air release pipe 33, and the grouting pipe 34 are all tightly connected with the pipeline, Form a sealed state, and the initial state of each valve is closed; open the valve of the vacuum tube 28 and start the vacuum pump 27 through the PLC assembly electric control box 30, and vacuumize the pipeline. When the vacuum in the pipeline is stable at the standard technical requirements When within the range, close the valve of the vacuum tube 28, di...