A kind of CFG pile prefabricated pile head and CFG pile construction method
A construction method and technology of prefabricated piles are applied in sheet pile wall, foundation structure engineering, construction and other directions, which can solve the problems of pile body breaking to below the design elevation of pile top, affecting construction period, wasting manpower, etc., so as to improve the bearing capacity of composite foundation. Eigenvalues, avoid secondary excavation of earthwork, and save the effect of engineering cost
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0031] The implementation of the present application will be described in detail below with reference to the accompanying drawings and examples, so as to fully understand and implement the implementation process of how the present application uses technical means to solve technical problems and achieve technical effects.
[0032] Such as figure 1 , Figure 2a and Figure 2b As shown, the prefabricated CFG pile head of the present application is a column structure, and the CFG pile head is prefabricated by reinforced concrete. After the pile head steel skeleton is formed, it is formed by pouring concrete.
[0033] Such as image 3 As shown, the top of the CFG pile head column structure also includes a pile head cap, which is prefabricated by reinforced concrete. The pile head cap and the CFG pile head column structure are an integrated structure, and three 8mm steel bars are distributed at the same angle through the same circle center to form the pile head. Cap reinforced s...