Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Beam replacement construction system of double-T beam bridge

A technology for transporting beams and corbel beams, which is applied in the field of beam replacement construction system of double T-beam bridges, and can solve the problems of existing lines such as greater impact on normal operation, high cost, and long construction period

Pending Publication Date: 2017-11-24
CHINA RAILWAY FIFTH SURVEY & DESIGN INST GRP
View PDF7 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] In view of the serious disease of old beams of some railway bridges in our country and the urgent need to replace them, in the past, in the construction of bridge replacements on existing railway lines, it was necessary to close the lines for a long time, and build temporary sidewalks or bridges for vehicles to pass at a speed limit , and then use the bridge erecting machine or erect brackets under the bridge to complete the construction work of hole-by-hole replacement. The cost is high, the construction period is long, the workload is heavy, and it has a great impact on the normal operation of the existing lines.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Beam replacement construction system of double-T beam bridge
  • Beam replacement construction system of double-T beam bridge
  • Beam replacement construction system of double-T beam bridge

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0032] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments It is a part of embodiments of the present invention, but not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0033] combine Figure 1 to Figure 3 As shown, the girder replacement construction system of a double T-shaped girder bridge provided by the embodiment of the present invention includes a girder replacement machine 4 arranged at the beam replacement position. The girder replacement machine 4 includes a main girder 42 on which There are two h...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to the technical field of beam replacement equipment of a double-T beam bridge and provides a beam replacement construction system of the double-T beam bridge. The beam replacement construction system comprises a beam replacement machine arranged at the position of beam replacement, the beam replacement machine comprises a main beam, two beam hanging carts capable of moving along the lengthwise direction of the main beam are arranged on the main beam, the main beam is erected on the bridge floor through a front guide pillar and a rear guide pillar, both the front guide pillar and the rear guide pillar are of telescopic structures, the beam replacement process is unaffected by natural conditions such as wind and cannot cause deviation to a fall beam, and beam replacement efficiency is improved; one set of special beam conveying trains, beam conveying carts and inverted gantries which are used for conveying an old beam and docking a new beam are respectively arranged on two sides of the beam replacement machine. By the arrangement, lifting height of the equipment can be effectively reduced during construction, team replacement of T-shaped beams is smoothly completed under the working conditions of construction limit requirements, and the fact that beam replacement construction of the full-span simply-supported T-shaped beams in a 'skylight point' is completed safely and efficiently on the premise of not causing any unnecessary impacts on original line equipment can be guaranteed.

Description

technical field [0001] The invention relates to the technical field of frame changing equipment for double T-shaped beam bridges, in particular to a beam changing construction system for double T-shaped beam bridges. Background technique [0002] In view of the serious disease of old beams of some railway bridges in our country and the urgent need to replace them, in the past, in the construction of bridge replacements on existing railway lines, it was necessary to close the lines for a long time, and build temporary sidewalks or bridges for vehicles to pass at a speed limit , and then use the bridge erecting machine or erect brackets under the bridge to complete the construction work of hole-by-hole frame replacement, which is costly, long-term, heavy workload, and has a great impact on the normal operation of existing lines. Contents of the invention [0003] The object of the present invention is to propose a beam replacement construction system that can safely and effi...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E01D21/00E01D2/00
CPCE01D2/00E01D21/00
Inventor 王治斌蒋中明王嵽显
Owner CHINA RAILWAY FIFTH SURVEY & DESIGN INST GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products