A technology of pre-splitting blasting and construction method, which is applied in blasting and other directions, and can solve problems such as landslides or landslides in small areas, affecting construction quality, safety, progress and driving safety, and large blasting crushing circles, so as to reduce secondary disasters caused by blasting and promote Self-stabilizing function, the effect of blocking blasting disturbance
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0031] see Figure 1-2 , a pre-splitting blasting construction method for deep hole slopes with buffer holes on parallel slopes. The specific construction process is: construction preparation→removal of overburden and scum→measurement and lofting→layout holes→production of slope ruler→installation of slope calibration frame→drilling → Preparation of pre-split blasting charge package → Charge charge → Blocking → Blasting network connection → Blasting warning → Ignition and detonation → Post-blasting inspection → Lifting the warning → Excavation and transportation of blasting slag.
[0032] Specific steps are as follows:
[0033] 1) Construction preparation: The operators and machines are in place on time and meet the start-up conditions.
[0034] 2) Removal of overburden and scum: According to the design requirements of flat field construction, remove existing pine rocks or topsoil layers on the site, expose the rocks, and meet the conditions for drilling and blasting. In the...