Suspension type well wall sinking construction method used for urban shaft construction
A construction method and a suspension-type technology are applied in the field of suspension-type shaft wall subsidence construction, which can solve the problems of shaft excavation direction deviation, shaft wall deviation, difficulty in lowering shaft wall, etc., so as to avoid deviation and improve the use of longevity, and the effect of avoiding excessive lateral static pressure of the formation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0025] In order to build an underground three-dimensional garage while reducing the amount of construction, the vertical shaft is usually selected as the construction space of the three-dimensional parking garage. In this embodiment, the suspended shaft wall sinking construction method for urban vertical shaft construction includes the following steps:
[0026] 1) Level the ground.
[0027] Before the excavation of the shaft shaft, it is necessary to level the surface of the excavation section of the shaft shaft to remove the sundries on the ground, and to level the ground at the excavation position of the shaft shaft to facilitate subsequent construction.
[0028] 2) Excavate the initial section of the shaft shaft.
[0029] In order to facilitate the lowering of the shaft wall 8, before the shaft shaft is excavated by large-scale excavating equipment, the initial section of the shaft shaft is excavated manually or by other small equipment.
[0030] 3) Build a concrete platfo...
Embodiment 2
[0044] The difference between the suspended shaft wall sinking construction method for urban shaft construction in this embodiment and the suspended shaft wall sinking construction method for urban shaft construction in Example 1 is: in step 6), Shaft well wall 8 is installed and comprises the steps:
[0045] 6.1) Install the shaft wall formwork on the shaft shaft wall blade foot 9;
[0046] 6.2) Pour concrete into the well wall formwork, and remove the well wall formwork after the concrete solidifies.
[0047] The shaft wall 8 can be poured with different concrete slurries according to the difference in the lateral static pressure of the formation that the shaft wall 8 is subjected to by concrete pouring.
[0048] In Embodiment 1 and Embodiment 2, the guiding system formed by using the vertical shaft wall blade foot 9, the vertical shaft shaft wall 8 and the lifting system for lowering the vertical shaft shaft wall can ensure that the shaft excavation direction is vertically...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com