Roller compacted concrete dam construction progress-cost cooperative control method based on BIM technology

A technology for roller compacted concrete and construction progress, which is applied in image data processing, special data processing applications, instruments, etc. It can solve the problems of lack of effective monitoring of progress and cost, weak linkage between construction progress and cost, and poor intuitiveness of construction simulation. , to achieve the effect of improving project management level and efficiency

Active Publication Date: 2019-05-03
CHINA THREE GORGES UNIV
View PDF2 Cites 16 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] The purpose of the present invention is to solve the problem of poor intuitiveness of roller compacted concrete dam construction simulation, weak linkage between construction progress and cost, and lack of control over progress and cost during the construction process. Effective monitoring, it is difficult to find deviations in time and adjust the implementation plan and other issues, provide a BIM technology-based RCC dam construction schedule-cost collaborative control method, realize the simulation of RCC dam construction schedule and cost; construction appearance, pouring Query strength and pouring resource usage information; monitor dynamic changes and early warnings of improved earned value indicators during the construction process, and realize virtual construction process visualization, construction schedule-cost simulation and collaborative control

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Roller compacted concrete dam construction progress-cost cooperative control method based on BIM technology
  • Roller compacted concrete dam construction progress-cost cooperative control method based on BIM technology
  • Roller compacted concrete dam construction progress-cost cooperative control method based on BIM technology

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0019] The construction schedule-cost collaborative control method for roller compacted concrete dams based on BIM technology includes the following steps:

[0020] Step 1: Establish a three-dimensional solid model for dam simulation: firstly, use three-dimensional modeling software to build a concrete pouring solid model of the dam based on actual engineering data;

[0021] Step 2: Compile the dam concrete pouring simulation information model, including the construction schedule, cost and resource information model;

[0022] Step 3: Import the 3D solid model and multiple information models of the dam simulation into the construction simulation platform, and integrate the RCC dam progress-cost collaborative management information platform through the association of data information;

[0023] Step 4: Simulate the concrete construction process of the dam based on the 3D solid model of the dam and schedule-cost information, display the implementation of the construction schedule ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

Roller compacted concrete dam construction progress-cost cooperative control method based on BIM technology comprises the following steps: establishing a dam simulation three-dimensional entity model;compiling a dam concrete pouring simulation information model; importing three-dimensional entity model and multiple information models of dam simulation into a construction simulation platform, andintegrating the roller compacted concrete dam progress-cost collaborative management information platform through correlation of data information; displaying the implementation conditions of the construction progress plan and the construction cost plan; monitoring an improved value index in the construction process by utilizing a secondarily developed platform plug-in and an improved value methodprinciple, and a project manager adjusting the construction progress-cost planning in time according to early warning information of monitoring deviation to achieve progress-cost correction, so as torealize collaborative management and control of the two, and finally, realizing a predetermined progress-cost target. By means of the method, visual simulation, construction information inquiry and tracking monitoring of the roller compacted concrete dam construction process can be achieved, a basis is provided for decision making and management of a project manager, and the construction progressis improved. And the cost management efficiency and the collaboration are improved.

Description

technical field [0001] The invention relates to the field of water conservancy and hydropower construction management and visualization, in particular to a BIM technology-based construction schedule-cost collaborative control method for a roller compacted concrete dam. Background technique [0002] Roller compacted concrete technology has developed rapidly. Because of its advantages such as fast construction speed, less cement consumption, low cost, safe and reliable quality, etc., it is widely used in large-scale water conservancy and hydropower projects, and the number of roller compacted concrete dams in my country is also increasing. . Nevertheless, the construction process of the RCC dam is a very complex system engineering, with high construction intensity, tight construction period, and strict construction process control requirements, which make the management and control of the RCC construction process difficult, and the schedule and cost objectives are mutually excl...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G06F17/50G06T17/00
Inventor 黄建文毛宇辰王兴霞袁华刘凯丽黄敏赵可欣熊鑫柏少哲陈梦媛陈萌姚茜郭松林宁武霆
Owner CHINA THREE GORGES UNIV
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products