Pile foundation construction method in narrow space

A construction method and technology of pile foundation, which can be applied in the direction of foundation structure engineering, sheet pile wall, building, etc., can solve the problems of high risk, narrow space, low construction efficiency, etc.

Inactive Publication Date: 2019-07-02
徐州盾安建筑工程机械制造有限公司
View PDF5 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Among them, the construction method of full casing and full rotary drilling rig has achieved good results in the construction of pile foundations in various complex geology, but with the construction of large-scale urban subway projects, the construction efficiency of traditional people and simple mechanical underground excavation pile foundations is low. And the risk is high. At the same time, the existing equipment on the market cannot enter the subway cavern for pile foundation construction due to structural dimensions and construction space constraints. Therefore, it is particularly important to design a pile foundation construction method in a narrow space.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Pile foundation construction method in narrow space
  • Pile foundation construction method in narrow space
  • Pile foundation construction method in narrow space

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0028] The pile foundation construction method in a narrow space of the present invention will be described in detail below in conjunction with the drawings.

[0029] See figure 1 , taking an underground cavern with low width and height as an example to illustrate the specific steps of the pile foundation construction method in a narrow space of the present invention. The width and height of such underground caverns are all limited, and conventional construction is relatively difficult.

[0030] See figure 2 image 3 , Step 1: Prepare the equipment. Provide the mechanical equipment required for construction and place them outside the underground cavern to be constructed. The mechanical equipment required for construction includes folding arm crane 1, power station 2, transfer vehicle 3, rotary drilling rig 4, soil borrowing device 5, casing 6, and steel bars The cage 7 and the conduit 8, in this embodiment, the rotary drilling rig 4 is an ultra-low altitude rotary drillin...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a pile foundation construction method in narrow space. The pile foundation construction method comprises the following steps that step 1, equipment is prepared, specifically, afolding arm crane, a power station, a transfer vehicle, a rotary drilling machine, a soil borrowing device, a sleeve, a reinforcement cage and a guide pipe are provided; step 2, hoisting and transferring are performed, specifically, the folding arm crane is used for hoisting the rotary drilling machine to the transfer vehicle; step 3, walking in position is performed, specifically, the transfer vehicle carries the rotary drilling machine and the folding arm crane pulls the power station to the predetermined position; step 4, leveling is performed, specifically, the rotary drilling machine issubjected to corrected the leveled; step 5, drilling and soil borrowing are performed, specifically, the rotary drilling machine holds and clamps the sleeve for hole drilling and the soil borrowing device is subjected to soil borrowing; step 6, the reinforcement cage is fixed, specifically, the reinforcement cage which is prefabricated in advance is hoisted and lowered and welded section by section until the reinforcement cage reaches the design position and is fixed; step 7, the guide pipe is inserted and subjected to concrete filling; and step 8, the construction is completed, specifically,after concrete pouring, the sleeve and the guide pipe are pulled out. The pile foundation construction method enables the pile foundation construction to be performed in the narrow space.

Description

technical field [0001] The invention relates to a construction method, in particular to a pile foundation construction method in a narrow space. Background technique [0002] With the development of society, the increase of large-scale infrastructure construction and high-rise buildings in China in recent years has led to an increasing number of pile foundation construction projects, and projects with special and complex working conditions are also emerging. Among them, the construction method of full casing and full rotary drilling rig has achieved good results in the construction of pile foundations in various complex geology, but with the construction of large-scale urban subway projects, the construction efficiency of traditional people and simple mechanical underground excavation pile foundations is low. And the risk is high. At the same time, the existing equipment on the market cannot enter the subway cavern for pile foundation construction due to structural dimension...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D5/36E02D15/04
CPCE02D5/36E02D15/04E02D2250/0023
Inventor 曹超王磊李志坚胡甲磊刘粱军
Owner 徐州盾安建筑工程机械制造有限公司