Steel pipe column structure house
A steel pipe column and residential technology, which is applied in the direction of building construction, construction, and building material processing, can solve the problems of insufficient connection strength, high cost, and large number of steel structures, and achieve the effect of improving connection stability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0038] Such as figure 1 As shown, this embodiment introduces a steel pipe structure residence, the main load-bearing structure includes a structural column 1 and a structural beam 2, the structural column 1 is a structural column 1 of a steel pipe structure, and the structural beam 2 is a structural beam 2 of a conventional steel bar structure, The main invention in this embodiment is to use a special connection structure to connect the structural column 1 of the steel pipe structure and the structural beam 2 of the steel structure, thereby improving the connection strength of the structural column 1 of the steel pipe structure and the structural beam 2 of the steel structure, Better connection strength is also achieved while saving costs.
[0039] Structural beam 2 can be prefabricated beam or cast-in-place beam, such as figure 1 As shown, the structural beam 2 includes a reinforcement cage, and reinforcing plates 3 are connected to the ends of the reinforcement cage. Such ...
Embodiment 2
[0049] This embodiment introduces a method for installing structural columns and structural beams of a steel pipe column structure house, mainly for the case that the structural beam 2 in the first embodiment is a prefabricated beam, including the following steps.
[0050] S1. The steel pipe structure of the structural column 1 is erected.
[0051] After the node columns 11 are vertically fixed, steel plates, steel pipes or I-shaped steel structures are used to reinforce the nodes columns 11, and the formed structural columns 1 are erected. Of course, the steel pipe structure is not limited to the above-mentioned cases.
[0052] S2. Set the reinforcing plate 3 on the reinforcing bars at both ends of the structural beam 2, so that the main reinforcing bars pass through the reinforcing bar holes 31 of the reinforcing plate 3, and then fix the reinforcing plate 3 and the main reinforcing bars.
[0053] The structure of the reinforcing plate 3 adopts the structure of Embodiment 1...
Embodiment 3
[0059] The difference from Embodiment 2 is that the structural beam 2 is a cast-in-place beam. When the structural beam 2 is erected in the early stage, the steel cage of the structural beam 2 is erected on the steel pipe structure of the structural column 1. The erection method and the embodiment The two are the same, the structural beam 2 is also poured and formed in step S5 during the forming process.