A Construction Method for Erecting Stiffened Beams Using Movable Cable Clamps
A construction method and a technology of stiffening beams, which are applied in the direction of erecting/assembling bridges, bridges, bridge construction, etc., can solve the problems of wasted construction period, complicated construction procedures, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0026] see figure 1 with figure 2 As shown, the embodiment of the present invention provides a construction method for erecting stiffened beams using movable cable clamps, including the following steps:
[0027] Step 101, install a slidable cable clamp 1 on the main cable 2 in the direction close to the main tower 7 (that is, the direction of the side span). 1 Just drive the stiffening beam segment 4 on the main cable 2 to move smoothly. Two groups of slidable cable clips 1 are symmetrically installed on the main cables 2 on both sides of the main tower 7 at the same height. Two sets of slidable cable clamps 1 can slide synchronously on the main cable 2 on both sides of the main tower to the mid-span direction, and use the brake device 6 to control the sliding and positioning of the slidable cable clamps 1 on the main cable 2 , realizing precise control of the sliding speed and fastening position of the slidable cable clamp 1 on the main cable 2 .
[0028] Step 102. Insta...
Embodiment 2
[0034] see figure 1 with figure 2 As shown, the embodiment of the present invention provides a construction method for erecting stiffened beams using movable cable clamps. Compared with embodiment 1, this embodiment differs in that the slidable cable clamp 1 cannot be clamped on the main cable 2 toward When sliding by itself in the mid-span direction, use the pulling device 5 to pull the slidable cable clamp 1 to the designed position, and then release the pulling device 5 . The pulling device 5 of this embodiment is preferably, but not limited to, a winch. The steel wire rope or chain on the winch is fixedly connected to the slidable cable clamp 1, and the pulling device 5 provides the slidable cable clamp 1 with traction in the mid-span direction. , improve construction efficiency.
Embodiment 3
[0036] see figure 1 with figure 2 As shown, the embodiment of the present invention provides a construction method for erecting stiffened beams using movable cable clamps. Compared with embodiment 1, the difference between this embodiment is that before the slidable cable clamp 1 and the main cable 2 are fastened, A gap is reserved between the slidable cable clamp 1 and the main cable 2, and the size of the gap is controllable by adjusting the tightening degree of the screw on the slidable cable clamp 1. In order to reduce the friction between the slidable cable clamp 1 and the main cable 2, lubricating oil or grease is applied on the contact surface of the slidable cable clamp 1 and the main cable 2 to reduce the friction between the slidable cable clamp 1 and the main cable 2. Wear between main cables 2.