Construction method for 360-degree rotary bend of sled track of snow vehicle
A construction method and sled technology, applied in the field of construction engineering, can solve problems such as difficult reinforcement of inclined columns, large changes in terrain height, and difficulty in formwork support
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0031] The construction method of the 360 ° turning curve of the bobsleigh track of the present invention comprises the following steps:
[0032] Step 1. Construct the oblique cylindrical cap according to the direction of the roundabout. After the construction of the cap is completed, the backfill earthwork shall be leveled and compacted, and the earthwork shall be backfilled to a height of 300mm below the top of the cap to form a foundation plane. The foundation plane shall be poured with C15 concrete for a 200mm thick cushion;
[0033] Step 2. Pre-buried ground anchors in the cushion layer. The ground anchors are arranged at 2m intervals along the roundabout section direction, and at 1m intervals along the roundabout within 5m from the root of the oblique cylinder projection range, and the rest are arranged at 3.6m intervals;
[0034] Step three, such as figure 1 As shown, the bottom boundary line 21 and the control line 22 of the inclined cylinder 2 are released on the cu...