Construction method of steel pipe prestressed steel strand passing through pipe at high altitude
A technology of prestressed steel strands and construction methods, which is applied in the processing of building materials, construction, building construction, etc., and can solve the problems of being unable to bypass obstacles, unsuitable for lifting grids, and strong hardness of steel casings
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment approach
[0046] When the continuous steel casing 31 and the continuous lower chord 11' are sheathed, the two ends of the steel strand bundle 20 are passed through the continuous steel sleeve 31 and the continuous lower chord 11' to form peeling section;
[0047] After the continuation of the steel casing 31 and the continuation of the lower chord 11' were all welded and fixed, the plastic jacket (such as image 3 shown), put on a temporary steel casing (not marked in the figure);
[0048] When preparing to set the anchor 70 at the stripping section, extract the temporary steel sleeve (such as image 3 extracted state).
[0049]Specifically, the peeling section is used to connect the main body of the structure to be spliced outside the network frame 10. In this embodiment, the main body of the structure to be spliced is a frame column 40, and usually the top of the frame column 40 is provided with a fixing bracket. Bearing ball 41, for the frame column 40 provided with bearing ba...