Early demolition enclosure system and its construction method
A technology of enclosure system and construction method, applied in excavation, infrastructure engineering, construction, etc., can solve the problems of affecting the enclosure structure, the main structure cannot be completed at one time, etc., and achieve the effect of convenient construction
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0035] The present invention will be further described below with reference to the accompanying drawings and specific embodiments.
[0036] see Figure 4 ,shown Figure 4 It is a schematic plan view of the early dismantling enclosure system of the present invention. Figure 5 for Figure 4 Enlarged perspective view of part B. Image 6 for Figure 5 Schematic diagram of the dismantled partition structure. combine Figure 4 to Figure 6 As shown, the early dismantling enclosure system of the present invention includes:
[0037] The supporting structure 10 surrounding the foundation pit;
[0038] The separation structure 20 is erected in the foundation pit, and the opposite ends of the separation structure 20 are fixed to the corresponding supporting structure 10 to realize the separation of the pit;
[0039] a support beam 30 laterally fixed to one side of the partition structure 20, and the opposite ends of the support beam 30 are fixed to the corresponding support struc...