A technology of geological environment and construction piles, applied in sheet pile walls, foundation structure engineering, buildings, etc., can solve the problems of high construction costs, achieve the effects of reducing construction difficulty, reducing usage, and reducing inconvenient transportation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0028] The present invention is described in detail below in conjunction with accompanying drawing:
[0029] Please refer to Figure 1 to Figure 3 , an embodiment of the present invention provides a method for constructing a pile foundation in a karst cave geological environment, which may include the following steps:
[0030] Step 310, measure the depth position and range of the cave 210 in the geological environment 200 according to the advanced drilling.
[0031] In step 320, hole-forming construction is carried out in the geological environment 200, and the depth position and range of the karst cave 210 are remeasured.
[0032] Step 330, according to the depth position of the karst cave 210 in the geological environment 200, the pile hole integrated retaining wall is set on the outer contour surface of the steel cage 110; the height dimension of the pile hole integrated retaining wall is greater than the height dimension of the karst cave 210, and the pile hole The integ...