Construction technology capable of repeatedly utilizing well cementation casing pipe
A construction technology and casing technology, applied in wellbore/well components, sealing/isolation, earthwork drilling and production, etc., can solve problems such as waste of resources, economic loss, and increase in project operating costs, so as to reduce operating costs and avoid The effect of wasting resources
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2021-10-08
Abstract
Description
technical field
[0001] The invention relates to the field of regional control drilling, in particular to a construction technique for reusable cementing casing. Background technique
[0002] In the existing traditional regional governance, the main hole construction adopts the full cementing construction method of lowering the multi-stage casing and returning the cement slurry to the ground. After the construction is completed, the casing will no longer play other functions, which will easily cause waste of resources and increase project operating costs; in addition In the event of an incorrect layer under the casing, the casing of the entire hole section cannot be recovered, resulting in large economic losses. Contents of the invention
[0003] The technical problem to be solved by the present invention is to provide a construction process of reusable cementing casing, which effectively overcomes the defects of the prior art.
[0004] The technical scheme that the presen...
Examples
Embodiment
[0035] Embodiment: The construction technology of the reusable cementing casing of this embodiment is characterized in that it includes the following steps:
[0036] Step 1. Drilling to 20m above the bedrock, and running a casing. The casing below the bedrock and the casing above the bedrock adopt opposite threaded joints, as follows:
[0037] S1. First use the through-hole tool to test (go down into the well). If the test process is smooth, go directly to the bottom of the hole. If there is an obstacle, lift it up 1-2m, turn on the pump to circulate, and sweep the hole in the forward direction. After passing through smoothly, then Lift it up, then sweep through the hole, repeat the above steps several times to ensure that the lower tube is unobstructed;
[0038] S2. Weld the water stop to the upper part of the swirl nipple, install the positive and negative joints, and spot weld the positive and negative joints with the anti-buckle seam of the water stop;