A construction method and water-retaining platform technology, applied to building components, building insulation materials, etc., can solve problems such as poor stability, high technical level requirements, and inconvenient construction methods of water-retaining platforms, so as to save construction time, beautiful shape, and overall good stability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0026] The construction method of the electric shaft bridge of the present invention through the floor slab retaining platform comprises the following steps:
[0027] a. The prefabricated concrete member with a Π-shaped cross-section includes the following steps:
[0028] (1) Determine the prefabricated Π-shaped concrete member according to the size of the opening of the electrical shaft.
[0029] see now figure 1 , figure 1 It is a structural schematic diagram of a Π-shaped concrete member according to an embodiment of the present invention. As shown in the figure, the Π-shaped concrete member is provided with a panel 1 and side panels 2 on both sides.
[0030] (2) Support the formwork and pour concrete according to the Π-shaped concrete member, and when the poured Π-shaped concrete member reaches half the height, insert the pre-embedded right-angled steel bars 3 respectively in the two right-angled corners of the concrete member to increase the Π Shaped concrete member s...