Construction method for support part to early dismount for super large area deep foundation pit

A super-large area and construction method technology, applied in infrastructure engineering, excavation, construction, etc., can solve problems such as affecting the construction progress of high-rise buildings and taking a long time, reducing management costs and construction costs, and producing rational and scientific production organization. , The effect of reducing the construction period

Active Publication Date: 2008-10-29
SHANGHAI CONSTR NO 5 GRP CO LTD
View PDF0 Cites 9 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

At present, in the field of construction, we often encounter buildings that need to be constructed separately due to different underground structures. The more common underground structure of buildings is the combination of underground garages and basements of high-rise buildings. High-rise basements must be removed after the first support of the foundation pit is removed. Construction, due to the large construction area of ​​the underground garage, it will take a long time from excavation to the completion of the underground structure of the garage, which will inevitably affect the construction progress of the high-rise building

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention belongs to the building construction technology field, and discloses a construction method used for early-dismantling the supporting local part of a super large excavation. The method includes the following steps: firstly, according to the construction area of the high part, the concrete first horizontal steel support influencing the high rise building construction is determined, and is taken as an object to be dismantled; secondly, after a foundation base plate is completed, a bracing bar is arranged on the lower side of the horizontal support to be dismantled; and thirdly, after the supporting bar is pre-stressed, the relevant first horizontal steel support to be dismantled in the step one is dismantled. Adopting the construction method of the invention can carry out balanced engineering construction on a continuous basis, save energy and reduce energy consumption, thereby laying a good foundation for accomplishing the construction period in advance or on time, and providing possibility to the early construction of the local high part of the super large excavation.

Description

Construction method of local early demolition of support for super large area deep foundation pit technical field The invention belongs to the technical field of building construction, and relates to a construction method, in particular to a support partial early demolition construction method for a super-large-area deep foundation pit. Background technique At present, in the field of construction, we often encounter buildings that need to be constructed separately due to different underground structures. The more common underground structure of buildings is the combination of underground garages and basements of high-rise buildings. High-rise basements must be removed after the first support of the foundation pit is removed. Construction, due to the large construction area of ​​the underground garage, it will take a long time from excavation to the completion of the underground structure of the garage, which will inevitably affect the construction progress of the high-rise...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E02D17/02
Inventor 毛子成张翼德丁利峰熊玎玮朱煜
Owner SHANGHAI CONSTR NO 5 GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Eureka Blog
Learn More
PatSnap group products