[0011] The implementation steps of the inventive method are described in detail below according to the accompanying drawings:
[0012] 1. First, when pouring concrete, leave a square hole 2 or a round hole in the place where the casing needs to be buried. The side length or hole diameter is about 30cm larger than the pipe diameter 1, such as figure 1 As shown, in this step, it is better for the structure to leave round holes, but the construction formwork is more complicated and can be selected according to needs. Regardless of whether it is a square hole or a round hole, the steel bars must be strengthened according to the requirements of the concrete specification. This step is similar to the method of reserving the casing.
[0013] 2. For particularly important parts or parts with relatively high water pressure, a steel plate water stop sheet 3 should also be buried in the middle of the pool wall where the hole is left. This step is not required for general parts, such as ...