Embodiment Construction
[0014] Such as figure 1 , figure 2 and image 3 As shown, the caisson 1 is generally divided into multiple compartments 10 through the partition wall 12 on the plane. First, one or more circles of deep-water wells 2 are staggered around the caisson 1 according to the analysis and calculation of underground hydrology. The deep-water wells in the same circle 2, the groundwater level of the caisson is maintained at a relatively stable groundwater level maintenance state 6 through the dewatering of the deep well 2. Then pour water into the caisson 1 and maintain a water level difference between the caisson 1 and the deep water well 2, place a floating box platform 9 in each compartment 10 inside the caisson 1 as a construction work platform, and place it below the floating box platform 9 The high-pressure water jet 4 and the mud pump 5 are suspended, the high-pressure water jet 4 is connected to the high-pressure water inlet pipe 3, and the mud pump 5 is connected to the mud dr...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com